Verano By Prescott construction photos
40 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Verano By Prescott was built on the day of each visit.
29 September 202641% built
2 July 202633% built
19 March 202620% built
18 December 202515% built
16 October 20256.5% built
27 May 20251.7% built
25 October 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.