Laya Courtyard construction progress
Laya Courtyard in Dubai Studio City is 51% built at the Land Department inspection of September 2026. Developer Laya Developers. Completion registered for December 2026.
51%
Built, at the Land Department site inspection of 15 September 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- July 2028
- Construction started
- October 2023
- Registered with the Land Department
- June 2024
- Developer
- Laya Developers
- Community
- Dubai Studio City
- Units
- 289
- Escrow bank
- Emirates NBD
- Name in Arabic
- لايا كورتيارد
- Land Department project number
- 2871
- Land Department site inspections
- 5
Schedule
Between December 2025 and September 2026 the site added about 2.2 points a month. At that rate it would finish around July 2028, more than three months after the December 2026 date registered with the Land Department.
Site inspections
15 September 2026
51%+14 pts
23 March 2026
37%+6.3 pts
15 December 2025
31%+12 pts
28 August 2025
19%+19 pts
13 February 2024
0%
Context
Dubai Studio City has 8 projects under construction, 51% built on average.
Own a unit in Laya Courtyard?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Laya Courtyard be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around July 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Laya Courtyard is built?
- 51%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 5 times since February 2024.
- Is Laya Courtyard delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Laya Courtyard?
- The registered developer is Laya Developers.
- Which bank holds the escrow account for Laya Courtyard?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosNearby in Dubai Studio City. 91%, Due April 2026, passed.
- Beach Oasis 2Nearby in Dubai Studio City. 53%, Due April 2026, passed.
- Arisha TerracesNearby in Dubai Studio City. 34%, Due October 2027.
- Ghaff Land ResidenceNearby in Dubai Studio City. 64%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.