Serene Gardens By Prescott construction progress

No completion date is registered for Serene Gardens By Prescott in Discovery Gardens yet. At the last site inspection, in September 2026, it was 62% built. The developer is Prescott Real Estate Development.

62%

Built, at the site inspection of 29 September 2026

Finish at recent pace
August 2027
Construction started
September 2023
First registered
September 2023
Units
184
Escrow bank
Mashreq Bank
Name in Arabic
سيرين جاردنز من بريسكوت
Project number
2740
Site inspections
9

Schedule

Since October 2025 Serene Gardens By Prescott has added about 3.7 points a month. At that rate the site reaches 100% around August 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

29 September 2026

62%+9.6 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 29 September 2026
  • Serene Gardens By Prescott construction site, inspection photo 2, 29 September 2026
  • Serene Gardens By Prescott construction site, inspection photo 3, 29 September 2026
  • Serene Gardens By Prescott construction site, inspection photo 4, 29 September 2026

29 June 2026

52%+13 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 29 June 2026
  • Serene Gardens By Prescott construction site, inspection photo 2, 29 June 2026
  • Serene Gardens By Prescott construction site, inspection photo 3, 29 June 2026
  • Serene Gardens By Prescott construction site, inspection photo 4, 29 June 2026

18 March 2026

39%+9.1 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 18 March 2026
  • Serene Gardens By Prescott construction site, inspection photo 2, 18 March 2026
  • Serene Gardens By Prescott construction site, inspection photo 3, 18 March 2026
  • Serene Gardens By Prescott construction site, inspection photo 4, 18 March 2026

17 December 2025

30%+12 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 17 December 2025
  • Serene Gardens By Prescott construction site, inspection photo 2, 17 December 2025
  • Serene Gardens By Prescott construction site, inspection photo 3, 17 December 2025
  • Serene Gardens By Prescott construction site, inspection photo 4, 17 December 2025

1 October 2025

18%+6.0 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 1 October 2025
  • Serene Gardens By Prescott construction site, inspection photo 2, 1 October 2025
  • Serene Gardens By Prescott construction site, inspection photo 3, 1 October 2025
  • Serene Gardens By Prescott construction site, inspection photo 4, 1 October 2025

18 June 2025

12%+6.3 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 18 June 2025
  • Serene Gardens By Prescott construction site, inspection photo 2, 18 June 2025
  • Serene Gardens By Prescott construction site, inspection photo 3, 18 June 2025
  • Serene Gardens By Prescott construction site, inspection photo 4, 18 June 2025

7 March 2025

5.6%+5.4 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 7 March 2025
  • Serene Gardens By Prescott construction site, inspection photo 2, 7 March 2025
  • Serene Gardens By Prescott construction site, inspection photo 3, 7 March 2025
  • Serene Gardens By Prescott construction site, inspection photo 4, 7 March 2025

26 September 2024

0.2%+0.2 pts

  • Serene Gardens By Prescott construction site, inspection photo 1, 26 September 2024
  • Serene Gardens By Prescott construction site, inspection photo 2, 26 September 2024
  • Serene Gardens By Prescott construction site, inspection photo 3, 26 September 2024

2 August 2023

0%

  • Serene Gardens By Prescott construction site, inspection photo 1, 2 August 2023
  • Serene Gardens By Prescott construction site, inspection photo 2, 2 August 2023
  • Serene Gardens By Prescott construction site, inspection photo 3, 2 August 2023

All 56 site photos, by inspection date

Context

Discovery Gardens has 9 projects under construction, 48% built on average.

Prescott Real Estate Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Serene Gardens By Prescott?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Serene Gardens By Prescott handover date?
No completion date is on record for Serene Gardens By Prescott yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Serene Gardens By Prescott?
Serene Gardens By Prescott was 62% built at the site inspection on 29 September 2026. The site has been inspected 9 times since August 2023. The Land Department took 56 site photos at its inspections.
Who is building Serene Gardens By Prescott?
The registered developer is Prescott Real Estate Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Serene Gardens By Prescott?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.