Off-plan projects in Dubai Studio City
8 projects in Dubai Studio City are under construction according to the Dubai Land Department. On average they are 51% built. 3 have passed their registered completion date. The next one due is Laya Courtyard, in December 2026.
- Samana MykonosSamana International Real Estate Development91%Due April 2026, passed
- Ghaff Land ResidenceGhaff Land Real Estate Development64%No date set
- Ryah Living By AlyakkaAlyakka Developers54%Due July 2026, passed
- Beach Oasis 2Azizi Developments53%Due April 2026, passed
- Laya CourtyardLaya Developers51%Due December 2026
- Verano By PrescottPrescott Real Estate Development41%Due December 2026
- Arisha TerracesQube Development34%Due October 2027
- The First Collection At Dubai Studio CityTfg S C Development21%Due January 2028
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.