Samana Mykonos construction photos

66 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Samana Mykonos was built on the day of each visit.

29 September 202691% built

20 May 202681% built

4 February 202667% built

24 November 202565% built

16 July 202555% built

17 February 202538% built

31 October 202423% built

7 May 202411% built

20 January 20230% built

Back to Samana Mykonos construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.