Ghaff Land Residence construction progress
Ghaff Land Residence in Dubai Studio City was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 66% built. The developer is Ghaff Land Real Estate Development.
66%
Built, at the site inspection of 13 October 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- December 2028
- Construction started
- January 2024
- First registered
- January 2025
- Developer
- Ghaff Land Real Estate Development
- Community
- Dubai Studio City
- Units
- 168
- Escrow bank
- Mashreq Bank
- Name in Arabic
- غاف لاند ريزيدنس
- Project number
- 3307
- Site inspections
- 6
Schedule
Ghaff Land Residence was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around December 2028.
Site inspections
13 October 2026
66%+2.0 pts
15 July 2026
64%+4.5 pts
5 March 2026
60%+8.0 pts
11 November 2025
52%+13 pts
1 July 2025
39%+16 pts
26 November 2024
23%
Context
Dubai Studio City has 8 projects under construction, 53% built on average.
Own a unit in Ghaff Land Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ghaff Land Residence handover date?
- The registered completion date was June 2026, and the register still lists Ghaff Land Residence as under construction. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ghaff Land Residence?
- Ghaff Land Residence was 66% built at the site inspection on 13 October 2026. The site has been inspected 6 times since November 2024. The Land Department took 46 site photos at its inspections.
- Is Ghaff Land Residence delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Ghaff Land Residence?
- The registered developer is Ghaff Land Real Estate Development.
- Which bank holds the escrow account for Ghaff Land Residence?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosNearby in Dubai Studio City. 91%, Due April 2026, passed.
- Laya CourtyardNearby in Dubai Studio City. 51%, Due December 2026.
- Beach Oasis 2Nearby in Dubai Studio City. 57%, Due April 2026, passed.
- Arisha TerracesNearby in Dubai Studio City. 34%, Due October 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.









.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)