Skip to content

Ghaff Land Residence construction progress

Ghaff Land Residence in Dubai Studio City was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 66% built. The developer is Ghaff Land Real Estate Development.

66%

Built, at the site inspection of 13 October 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
December 2028
Construction started
January 2024
First registered
January 2025
Developer
Ghaff Land Real Estate Development
Units
168
Escrow bank
Mashreq Bank
Name in Arabic
غاف لاند ريزيدنس
Project number
3307
Site inspections
6

Schedule

Ghaff Land Residence was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around December 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 October 2026

66%+2.0 pts

  • Ghaff Land Residence construction site, inspection photo 1, 13 October 2026
  • Ghaff Land Residence construction site, inspection photo 2, 13 October 2026
  • Ghaff Land Residence construction site, inspection photo 3, 13 October 2026
  • Ghaff Land Residence construction site, inspection photo 4, 13 October 2026

15 July 2026

64%+4.5 pts

  • Ghaff Land Residence construction site, inspection photo 1, 15 July 2026
  • Ghaff Land Residence construction site, inspection photo 2, 15 July 2026
  • Ghaff Land Residence construction site, inspection photo 3, 15 July 2026
  • Ghaff Land Residence construction site, inspection photo 4, 15 July 2026

5 March 2026

60%+8.0 pts

  • Ghaff Land Residence construction site, inspection photo 1, 5 March 2026
  • Ghaff Land Residence construction site, inspection photo 2, 5 March 2026
  • Ghaff Land Residence construction site, inspection photo 3, 5 March 2026
  • Ghaff Land Residence construction site, inspection photo 4, 5 March 2026

11 November 2025

52%+13 pts

  • Ghaff Land Residence construction site, inspection photo 1, 11 November 2025
  • Ghaff Land Residence construction site, inspection photo 2, 11 November 2025
  • Ghaff Land Residence construction site, inspection photo 3, 11 November 2025
  • Ghaff Land Residence construction site, inspection photo 4, 11 November 2025

1 July 2025

39%+16 pts

  • Ghaff Land Residence construction site, inspection photo 1, 1 July 2025
  • Ghaff Land Residence construction site, inspection photo 2, 1 July 2025
  • Ghaff Land Residence construction site, inspection photo 3, 1 July 2025
  • Ghaff Land Residence construction site, inspection photo 4, 1 July 2025

26 November 2024

23%

  • Ghaff Land Residence construction site, inspection photo 1, 26 November 2024
  • Ghaff Land Residence construction site, inspection photo 2, 26 November 2024
  • Ghaff Land Residence construction site, inspection photo 3, 26 November 2024
  • Ghaff Land Residence construction site, inspection photo 4, 26 November 2024

All 46 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Own a unit in Ghaff Land Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ghaff Land Residence handover date?
The registered completion date was June 2026, and the register still lists Ghaff Land Residence as under construction. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ghaff Land Residence?
Ghaff Land Residence was 66% built at the site inspection on 13 October 2026. The site has been inspected 6 times since November 2024. The Land Department took 46 site photos at its inspections.
Is Ghaff Land Residence delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Ghaff Land Residence?
The registered developer is Ghaff Land Real Estate Development.
Which bank holds the escrow account for Ghaff Land Residence?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.