Azizi Vista construction progress

The register lists Azizi Vista in Dubai Studio City as complete, with a registered completion date of April 2025. Its last site inspection on record was in August 2025. The developer is Azizi Developments.

100%

Built, at the site inspection of 30 August 2025

Construction complete

Registered completion date
April 2025
Construction started
April 2023
First registered
June 2023
Units
163
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزى فيستا
Project number
2650
Site inspections
4

Schedule

The register lists Azizi Vista as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 August 2025

100%+10 pts

  • Azizi Vista construction site, inspection photo 1, 30 August 2025
  • Azizi Vista construction site, inspection photo 2, 30 August 2025
  • Azizi Vista construction site, inspection photo 3, 30 August 2025
  • Azizi Vista construction site, inspection photo 4, 30 August 2025

6 May 2025

90%+39 pts

  • Azizi Vista construction site, inspection photo 1, 6 May 2025
  • Azizi Vista construction site, inspection photo 2, 6 May 2025
  • Azizi Vista construction site, inspection photo 3, 6 May 2025
  • Azizi Vista construction site, inspection photo 4, 6 May 2025

3 June 2024

51%+36 pts

  • Azizi Vista construction site, inspection photo 1, 3 June 2024
  • Azizi Vista construction site, inspection photo 2, 3 June 2024
  • Azizi Vista construction site, inspection photo 3, 3 June 2024
  • Azizi Vista construction site, inspection photo 4, 3 June 2024

11 May 2023

15%

  • Azizi Vista construction site, inspection photo 1, 11 May 2023
  • Azizi Vista construction site, inspection photo 2, 11 May 2023
  • Azizi Vista construction site, inspection photo 3, 11 May 2023
  • Azizi Vista construction site, inspection photo 4, 11 May 2023

All 41 site photos, by inspection date

Context

Dubai Studio City has 8 projects under construction, 53% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Vista?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Vista handover date?
Construction of Azizi Vista is recorded as complete, with a registered completion date of April 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Vista?
Azizi Vista was 100% built at the site inspection on 30 August 2025. The site has been inspected 4 times since May 2023. The Land Department took 41 site photos at its inspections.
Is Azizi Vista delayed?
The register lists construction as complete.
Who is building Azizi Vista?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Vista?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.