Vida Residences Dubai Marina construction progress

The register lists Vida Residences Dubai Marina in Dubai Marina as complete, with a registered completion date of November 2022. Its last site inspection on record was in December 2022. The developer is Emaar Development.

100%

Built, at the site inspection of 14 December 2022

Construction complete

Registered completion date
November 2022
Construction started
April 2017
First registered
November 2016
Community
Dubai Marina
Units
365
Escrow bank
Dubai Islamic Bank
Name in Arabic
فيدا ريزيدنسز دبي مارينا
Project number
1831
Site inspections
17

Schedule

The register lists Vida Residences Dubai Marina as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 December 2022

100%+7.3 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 14 December 2022
  • Vida Residences Dubai Marina construction site, inspection photo 2, 14 December 2022
  • Vida Residences Dubai Marina construction site, inspection photo 3, 14 December 2022
  • Vida Residences Dubai Marina construction site, inspection photo 4, 14 December 2022

31 August 2022

93%+4.6 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 31 August 2022
  • Vida Residences Dubai Marina construction site, inspection photo 2, 31 August 2022
  • Vida Residences Dubai Marina construction site, inspection photo 3, 31 August 2022
  • Vida Residences Dubai Marina construction site, inspection photo 4, 31 August 2022

17 May 2022

88%+10 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 17 May 2022
  • Vida Residences Dubai Marina construction site, inspection photo 2, 17 May 2022
  • Vida Residences Dubai Marina construction site, inspection photo 3, 17 May 2022
  • Vida Residences Dubai Marina construction site, inspection photo 4, 17 May 2022

4 November 2021

78%+6.6 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 4 November 2021
  • Vida Residences Dubai Marina construction site, inspection photo 2, 4 November 2021
  • Vida Residences Dubai Marina construction site, inspection photo 3, 4 November 2021
  • Vida Residences Dubai Marina construction site, inspection photo 4, 4 November 2021

5 July 2021

71%+7.1 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 5 July 2021
  • Vida Residences Dubai Marina construction site, inspection photo 2, 5 July 2021
  • Vida Residences Dubai Marina construction site, inspection photo 3, 5 July 2021
  • Vida Residences Dubai Marina construction site, inspection photo 4, 5 July 2021

25 April 2021

64%+10 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 25 April 2021
  • Vida Residences Dubai Marina construction site, inspection photo 2, 25 April 2021
  • Vida Residences Dubai Marina construction site, inspection photo 3, 25 April 2021
  • Vida Residences Dubai Marina construction site, inspection photo 4, 25 April 2021

14 January 2021

54%+8.0 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 14 January 2021
  • Vida Residences Dubai Marina construction site, inspection photo 2, 14 January 2021
  • Vida Residences Dubai Marina construction site, inspection photo 3, 14 January 2021
  • Vida Residences Dubai Marina construction site, inspection photo 4, 14 January 2021

23 September 2020

46%+6.0 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 23 September 2020
  • Vida Residences Dubai Marina construction site, inspection photo 2, 23 September 2020
  • Vida Residences Dubai Marina construction site, inspection photo 3, 23 September 2020
  • Vida Residences Dubai Marina construction site, inspection photo 4, 23 September 2020

10 June 2020

40%+9.9 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 10 June 2020
  • Vida Residences Dubai Marina construction site, inspection photo 2, 10 June 2020
  • Vida Residences Dubai Marina construction site, inspection photo 3, 10 June 2020
  • Vida Residences Dubai Marina construction site, inspection photo 4, 10 June 2020

22 December 2019

30%+6.8 pts

  • Vida Residences Dubai Marina construction site, inspection photo 1, 22 December 2019
  • Vida Residences Dubai Marina construction site, inspection photo 2, 22 December 2019
  • Vida Residences Dubai Marina construction site, inspection photo 3, 22 December 2019
  • Vida Residences Dubai Marina construction site, inspection photo 4, 22 December 2019

All 163 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vida Residences Dubai Marina?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Vida Residences Dubai Marina handover date?
Construction of Vida Residences Dubai Marina is recorded as complete, with a registered completion date of November 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Vida Residences Dubai Marina?
Vida Residences Dubai Marina was 100% built at the site inspection on 14 December 2022. The site has been inspected 17 times since February 2018. The Land Department took 163 site photos at its inspections.
Is Vida Residences Dubai Marina delayed?
The register lists construction as complete.
Who is building Vida Residences Dubai Marina?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Vida Residences Dubai Marina?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.