The Residences At Marina Gate 1 construction progress
The register lists The Residences At Marina Gate 1 in Dubai Marina as complete, with a registered completion date of April 2018. Its last site inspection on record was in April 2018. The developer is Select Global Development.
100%
Built, at the site inspection of 2 April 2018
Construction complete
- Registered completion date
- April 2018
- Construction started
- May 2014
- First registered
- March 2014
- Developer
- Select Global Development
- Community
- Dubai Marina
- Units
- 415
- Escrow bank
- Mashreq Bank
- Name in Arabic
- ذا ريزيدنسز ات مارينا جيت 1
- Project number
- 1495
- Site inspections
- 10
Schedule
The register lists The Residences At Marina Gate 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
2 April 2018
100%+9.5 pts
29 October 2017
90%+10 pts
23 July 2017
80%+15 pts
14 February 2017
65%+16 pts
16 October 2016
49%+19 pts
30 May 2016
30%+5.1 pts
2 February 2016
25%+11 pts
6 August 2015
14%+5.1 pts
8 March 2015
9.0%+5.4 pts
16 December 2014
3.6%
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Residences At Marina Gate 1?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the The Residences At Marina Gate 1 handover date?
- Construction of The Residences At Marina Gate 1 is recorded as complete, with a registered completion date of April 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on The Residences At Marina Gate 1?
- The Residences At Marina Gate 1 was 100% built at the site inspection on 2 April 2018. The site has been inspected 10 times since December 2014. The Land Department took 66 site photos at its inspections.
- Is The Residences At Marina Gate 1 delayed?
- The register lists construction as complete.
- Who is building The Residences At Marina Gate 1?
- The registered developer is Select Global Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for The Residences At Marina Gate 1?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nautica OneAlso by Select Global Development. 85%.
- Nautica TwoAlso by Select Global Development. 85%.
- Six Senses Residences Dubai MarinaAlso by Select Global Development. 27%.
- Artistry One ResidencesAlso by Select Global Development. 0%, Due February 2029.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.











