Nautica One construction progress

Nautica One in Dubai Maritime City is 85% built at the Land Department inspection of September 2026. Developer Select Global Development.

85%

Built, at the Land Department site inspection of 3 September 2026

Finish at recent pace
December 2026
Construction started
October 2023
Registered with the Land Department
September 2023
Units
328
Escrow bank
Emirates NBD
Name in Arabic
نوتيكا ون
Land Department project number
2781
Land Department site inspections
9

Schedule

Since December 2025 Nautica One has added about 4.3 points a month. At that rate the site reaches 100% around December 2026. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

3 September 2026

85%+21 pts

  • Nautica One construction site, Land Department inspection photo 1, 3 September 2026
  • Nautica One construction site, Land Department inspection photo 2, 3 September 2026
  • Nautica One construction site, Land Department inspection photo 3, 3 September 2026
  • Nautica One construction site, Land Department inspection photo 4, 3 September 2026

24 April 2026

65%+18 pts

  • Nautica One construction site, Land Department inspection photo 1, 24 April 2026
  • Nautica One construction site, Land Department inspection photo 2, 24 April 2026
  • Nautica One construction site, Land Department inspection photo 3, 24 April 2026
  • Nautica One construction site, Land Department inspection photo 4, 24 April 2026

4 December 2025

47%+14 pts

  • Nautica One construction site, Land Department inspection photo 1, 4 December 2025
  • Nautica One construction site, Land Department inspection photo 2, 4 December 2025
  • Nautica One construction site, Land Department inspection photo 3, 4 December 2025
  • Nautica One construction site, Land Department inspection photo 4, 4 December 2025

27 August 2025

32%+8.1 pts

  • Nautica One construction site, Land Department inspection photo 1, 27 August 2025
  • Nautica One construction site, Land Department inspection photo 2, 27 August 2025
  • Nautica One construction site, Land Department inspection photo 3, 27 August 2025
  • Nautica One construction site, Land Department inspection photo 4, 27 August 2025

25 June 2025

24%+6.2 pts

  • Nautica One construction site, Land Department inspection photo 1, 25 June 2025
  • Nautica One construction site, Land Department inspection photo 2, 25 June 2025
  • Nautica One construction site, Land Department inspection photo 3, 25 June 2025
  • Nautica One construction site, Land Department inspection photo 4, 25 June 2025

27 February 2025

18%+11 pts

  • Nautica One construction site, Land Department inspection photo 1, 27 February 2025
  • Nautica One construction site, Land Department inspection photo 2, 27 February 2025
  • Nautica One construction site, Land Department inspection photo 3, 27 February 2025
  • Nautica One construction site, Land Department inspection photo 4, 27 February 2025

28 October 2024

7.3%+6.4 pts

  • Nautica One construction site, Land Department inspection photo 1, 28 October 2024
  • Nautica One construction site, Land Department inspection photo 2, 28 October 2024
  • Nautica One construction site, Land Department inspection photo 3, 28 October 2024
  • Nautica One construction site, Land Department inspection photo 4, 28 October 2024

1 May 2024

0.9%+0.9 pts

  • Nautica One construction site, Land Department inspection photo 1, 1 May 2024
  • Nautica One construction site, Land Department inspection photo 2, 1 May 2024
  • Nautica One construction site, Land Department inspection photo 3, 1 May 2024

19 September 2023

0%

  • Nautica One construction site, Land Department inspection photo 1, 19 September 2023
  • Nautica One construction site, Land Department inspection photo 2, 19 September 2023
  • Nautica One construction site, Land Department inspection photo 3, 19 September 2023
  • Nautica One construction site, Land Department inspection photo 4, 19 September 2023

All 62 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nautica One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Nautica One be completed?
The Land Department has no completion date on record for Nautica One yet.
How much of Nautica One is built?
85%, measured at the Land Department site inspection on 3 September 2026. The Land Department engineers have inspected the site 9 times since September 2023.
Who is building Nautica One?
The registered developer is Select Global Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Nautica One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.