Nautica Two construction progress
No completion date is registered for Nautica Two in Dubai Maritime City yet. At the last site inspection, in September 2026, it was 85% built. The developer is Select Global Development.
85%
Built, at the site inspection of 3 September 2026
- Finish at recent pace
- December 2026
- Construction started
- October 2023
- First registered
- October 2023
- Developer
- Select Global Development
- Community
- Dubai Maritime City
- Units
- 328
- Escrow bank
- Emirates NBD
- Name in Arabic
- نوتيكا تو
- Project number
- 2783
- Site inspections
- 9
Schedule
Since December 2025 Nautica Two has added about 4.4 points a month. At that rate the site reaches 100% around December 2026. No completion date is on record to compare it with.
Site inspections
3 September 2026
85%+21 pts
24 April 2026
64%+18 pts
4 December 2025
46%+14 pts
27 August 2025
32%+4.7 pts
25 June 2025
27%+12 pts
24 February 2025
15%+7.3 pts
28 October 2024
7.4%+6.3 pts
1 May 2024
1.1%+1.1 pts
19 September 2023
0%
Context
Dubai Maritime City has 23 projects under construction, 32% built on average.
Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Nautica Two?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Nautica Two handover date?
- No completion date is on record for Nautica Two yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Nautica Two?
- Nautica Two was 85% built at the site inspection on 3 September 2026. The site has been inspected 9 times since September 2023. The Land Department took 60 site photos at its inspections.
- Who is building Nautica Two?
- The registered developer is Select Global Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Nautica Two?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Nautica OneAlso by Select Global Development. 85%.
- Six Senses Residences Dubai MarinaAlso by Select Global Development. 27%.
- Artistry One ResidencesAlso by Select Global Development. 0%, Due February 2029.
- Artistry Two ResidencesAlso by Select Global Development. 0%, Due February 2029.
- Harbour LightsNearby in Dubai Maritime City. 72%, Due May 2027.
- Mar CasaNearby in Dubai Maritime City. 67%, Due October 2026, passed.
- Aria By BeyondNearby in Dubai Maritime City. 85%, Due January 2026, passed.
- Coral ReefNearby in Dubai Maritime City. 33%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



























.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)