Skip to content

Nautica Two construction progress

Nautica Two in Dubai Maritime City is 85% built at the Land Department inspection of September 2026. Developer Select Global Development.

85%

Built, at the Land Department site inspection of 3 September 2026

Finish at recent pace
December 2026
Construction started
October 2023
Registered with the Land Department
October 2023
Units
328
Escrow bank
Emirates NBD
Name in Arabic
نوتيكا تو
Land Department project number
2783
Land Department site inspections
9

Schedule

Since December 2025 Nautica Two has added about 4.4 points a month. At that rate the site reaches 100% around December 2026. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

3 September 2026

85%+21 pts

  • Nautica Two construction site, Land Department inspection photo 1, 3 September 2026
  • Nautica Two construction site, Land Department inspection photo 2, 3 September 2026
  • Nautica Two construction site, Land Department inspection photo 3, 3 September 2026
  • Nautica Two construction site, Land Department inspection photo 4, 3 September 2026

24 April 2026

64%+18 pts

  • Nautica Two construction site, Land Department inspection photo 1, 24 April 2026
  • Nautica Two construction site, Land Department inspection photo 2, 24 April 2026
  • Nautica Two construction site, Land Department inspection photo 3, 24 April 2026
  • Nautica Two construction site, Land Department inspection photo 4, 24 April 2026

4 December 2025

46%+14 pts

  • Nautica Two construction site, Land Department inspection photo 1, 4 December 2025
  • Nautica Two construction site, Land Department inspection photo 2, 4 December 2025
  • Nautica Two construction site, Land Department inspection photo 3, 4 December 2025
  • Nautica Two construction site, Land Department inspection photo 4, 4 December 2025

27 August 2025

32%+4.7 pts

  • Nautica Two construction site, Land Department inspection photo 1, 27 August 2025
  • Nautica Two construction site, Land Department inspection photo 2, 27 August 2025
  • Nautica Two construction site, Land Department inspection photo 3, 27 August 2025
  • Nautica Two construction site, Land Department inspection photo 4, 27 August 2025

25 June 2025

27%+12 pts

  • Nautica Two construction site, Land Department inspection photo 1, 25 June 2025
  • Nautica Two construction site, Land Department inspection photo 2, 25 June 2025
  • Nautica Two construction site, Land Department inspection photo 3, 25 June 2025
  • Nautica Two construction site, Land Department inspection photo 4, 25 June 2025

24 February 2025

15%+7.3 pts

  • Nautica Two construction site, Land Department inspection photo 1, 24 February 2025
  • Nautica Two construction site, Land Department inspection photo 2, 24 February 2025
  • Nautica Two construction site, Land Department inspection photo 3, 24 February 2025
  • Nautica Two construction site, Land Department inspection photo 4, 24 February 2025

28 October 2024

7.4%+6.3 pts

  • Nautica Two construction site, Land Department inspection photo 1, 28 October 2024
  • Nautica Two construction site, Land Department inspection photo 2, 28 October 2024
  • Nautica Two construction site, Land Department inspection photo 3, 28 October 2024
  • Nautica Two construction site, Land Department inspection photo 4, 28 October 2024

1 May 2024

1.1%+1.1 pts

  • Nautica Two construction site, Land Department inspection photo 1, 1 May 2024
  • Nautica Two construction site, Land Department inspection photo 2, 1 May 2024
  • Nautica Two construction site, Land Department inspection photo 3, 1 May 2024

19 September 2023

0%

  • Nautica Two construction site, Land Department inspection photo 1, 19 September 2023
  • Nautica Two construction site, Land Department inspection photo 2, 19 September 2023
  • Nautica Two construction site, Land Department inspection photo 3, 19 September 2023

All 60 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nautica Two?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Nautica Two be completed?
The Land Department has no completion date on record for Nautica Two yet.
How much of Nautica Two is built?
85%, measured at the Land Department site inspection on 3 September 2026. The Land Department engineers have inspected the site 9 times since September 2023.
Who is building Nautica Two?
The registered developer is Select Global Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Nautica Two?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.