The Residences At Marina Gate 1 construction photos
66 photos from 10 site inspections, newest first. The percentage is how much of The Residences At Marina Gate 1 was built on the day of each visit.
2 April 2018100% built
29 October 201790% built
23 July 201780% built
14 February 201765% built
16 October 201649% built
30 May 201630% built
2 February 201625% built
6 August 201514% built
8 March 20159.0% built
16 December 20143.6% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.