Time 2 construction progress
Time 2 in Dubai Land Residence Complex is 87% built at the Land Department inspection of April 2026. Developer Time Properties. Completion registered for June 2026.
87%
Built, at the Land Department site inspection of 28 April 2026
4 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- August 2026
- Construction started
- January 2023
- Registered with the Land Department
- February 2023
- Developer
- Time Properties
- Community
- Dubai Land Residence Complex
- Units
- 304
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- تايم 2
- Land Department project number
- 2541
- Land Department site inspections
- 8
Schedule
Time 2 was registered to complete in June 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around August 2026.
Site inspections
28 April 2026
87%+15 pts
8 December 2025
72%+13 pts
31 July 2025
59%+14 pts
25 February 2025
45%+14 pts
8 November 2024
31%+8.8 pts
4 June 2024
22%+4.2 pts
14 March 2024
18%+18 pts
20 December 2022
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Time 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Time 2 be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around August 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Time 2 is built?
- 87%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 8 times since December 2022.
- Is Time 2 delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Time 2?
- The registered developer is Time Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Time 2?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Time 3Also by Time Properties. 47%, Due August 2027.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Samana Ivy GardensNearby in Dubai Land Residence Complex. 41%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)







.jpg&w=3840&q=75)