Time 2 construction progress
Time 2 in Dubai Land Residence Complex was registered to complete in June 2026 and is still under construction. At the last site inspection, in April 2026, it was 87% built. The developer is Time Properties.
87%
Built, at the site inspection of 28 April 2026
6 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- August 2026
- Construction started
- January 2023
- First registered
- February 2023
- Developer
- Time Properties
- Community
- Dubai Land Residence Complex
- Units
- 304
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- تايم 2
- Project number
- 2541
- Site inspections
- 8
Schedule
Time 2 was registered to complete in June 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around August 2026.
Site inspections
28 April 2026
87%+15 pts
8 December 2025
72%+13 pts
31 July 2025
59%+14 pts
25 February 2025
45%+14 pts
8 November 2024
31%+8.8 pts
4 June 2024
22%+4.2 pts
14 March 2024
18%+18 pts
20 December 2022
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Time 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Time 2 handover date?
- The registered completion date was June 2026, and the register still lists Time 2 as under construction. At the pace of its recent inspections the site would reach 100% around August 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Time 2?
- Time 2 was 87% built at the site inspection on 28 April 2026. The site has been inspected 8 times since December 2022. The Land Department took 61 site photos at its inspections.
- Is Time 2 delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Time 2?
- The registered developer is Time Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Time 2?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Time 3Also by Time Properties. 47%, Due August 2027.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Samana Ivy GardensNearby in Dubai Land Residence Complex. 41%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)





.jpg&w=3840&q=75)