Ag Central construction progress

Ag Central in Dubai Land Residence Complex is 59% built at the Land Department inspection of September 2026. Developer Ag Properties. Completion registered for October 2026.

59%

Built, at the Land Department site inspection of 17 September 2026

Running behind its date

Completion date (Land Department)
October 2026
Finish at recent pace
June 2030
Construction started
October 2023
Registered with the Land Department
November 2023
Developer
Ag Properties
Units
96
Escrow bank
Emirates NBD
Name in Arabic
ايه جي سينترال
Land Department project number
2422
Land Department site inspections
6

Schedule

Between October 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around June 2030, more than three months after the October 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 September 2026

59%+7.8 pts

  • Ag Central construction site, Land Department inspection photo 1, 17 September 2026
  • Ag Central construction site, Land Department inspection photo 2, 17 September 2026
  • Ag Central construction site, Land Department inspection photo 3, 17 September 2026
  • Ag Central construction site, Land Department inspection photo 4, 17 September 2026

9 February 2026

51%+2.5 pts

  • Ag Central construction site, Land Department inspection photo 1, 9 February 2026
  • Ag Central construction site, Land Department inspection photo 2, 9 February 2026
  • Ag Central construction site, Land Department inspection photo 3, 9 February 2026
  • Ag Central construction site, Land Department inspection photo 4, 9 February 2026

13 October 2025

48%+10 pts

  • Ag Central construction site, Land Department inspection photo 1, 13 October 2025
  • Ag Central construction site, Land Department inspection photo 2, 13 October 2025
  • Ag Central construction site, Land Department inspection photo 3, 13 October 2025
  • Ag Central construction site, Land Department inspection photo 4, 13 October 2025

21 March 2025

38%+14 pts

  • Ag Central construction site, Land Department inspection photo 1, 21 March 2025
  • Ag Central construction site, Land Department inspection photo 2, 21 March 2025
  • Ag Central construction site, Land Department inspection photo 3, 21 March 2025
  • Ag Central construction site, Land Department inspection photo 4, 21 March 2025

16 October 2024

24%+21 pts

  • Ag Central construction site, Land Department inspection photo 1, 16 October 2024
  • Ag Central construction site, Land Department inspection photo 2, 16 October 2024
  • Ag Central construction site, Land Department inspection photo 3, 16 October 2024
  • Ag Central construction site, Land Department inspection photo 4, 16 October 2024

18 September 2023

2.3%

  • Ag Central construction site, Land Department inspection photo 1, 18 September 2023
  • Ag Central construction site, Land Department inspection photo 2, 18 September 2023
  • Ag Central construction site, Land Department inspection photo 3, 18 September 2023
  • Ag Central construction site, Land Department inspection photo 4, 18 September 2023

All 39 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Ag Properties has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ag Central?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Ag Central be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around June 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ag Central is built?
59%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 6 times since September 2023.
Is Ag Central delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
Who is building Ag Central?
The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Ag Central?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.