Ag Square construction progress

Ag Square in Dubai Land Residence Complex was registered to complete in September 2026 and is still under construction. At the last site inspection, in September 2026, it was 69% built. The developer is Ag Properties.

69%

Built, at the site inspection of 17 September 2026

2 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
September 2027
Construction started
September 2022
First registered
October 2022
Developer
Ag Properties
Units
372
Escrow bank
Emirates NBD
Name in Arabic
ايه جي سكوير
Project number
2424
Site inspections
7

Schedule

Ag Square was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around September 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

69%+20 pts

  • Ag Square construction site, inspection photo 1, 17 September 2026
  • Ag Square construction site, inspection photo 2, 17 September 2026
  • Ag Square construction site, inspection photo 3, 17 September 2026
  • Ag Square construction site, inspection photo 4, 17 September 2026

9 February 2026

49%+11 pts

  • Ag Square construction site, inspection photo 1, 9 February 2026
  • Ag Square construction site, inspection photo 2, 9 February 2026
  • Ag Square construction site, inspection photo 3, 9 February 2026
  • Ag Square construction site, inspection photo 4, 9 February 2026

21 July 2025

39%+6.1 pts

  • Ag Square construction site, inspection photo 1, 21 July 2025
  • Ag Square construction site, inspection photo 2, 21 July 2025
  • Ag Square construction site, inspection photo 3, 21 July 2025
  • Ag Square construction site, inspection photo 4, 21 July 2025

28 February 2025

32%+8.9 pts

  • Ag Square construction site, inspection photo 1, 28 February 2025
  • Ag Square construction site, inspection photo 2, 28 February 2025
  • Ag Square construction site, inspection photo 3, 28 February 2025
  • Ag Square construction site, inspection photo 4, 28 February 2025

16 October 2024

24%+18 pts

  • Ag Square construction site, inspection photo 1, 16 October 2024
  • Ag Square construction site, inspection photo 2, 16 October 2024
  • Ag Square construction site, inspection photo 3, 16 October 2024
  • Ag Square construction site, inspection photo 4, 16 October 2024

13 November 2023

5.0%+5.0 pts

  • Ag Square construction site, inspection photo 1, 13 November 2023
  • Ag Square construction site, inspection photo 2, 13 November 2023
  • Ag Square construction site, inspection photo 3, 13 November 2023
  • Ag Square construction site, inspection photo 4, 13 November 2023

3 October 2022

0%

  • Ag Square construction site, inspection photo 1, 3 October 2022
  • Ag Square construction site, inspection photo 2, 3 October 2022
  • Ag Square construction site, inspection photo 3, 3 October 2022

All 42 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Ag Properties has 4 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Ag Square?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ag Square handover date?
The registered completion date was September 2026, and the register still lists Ag Square as under construction. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ag Square?
Ag Square was 69% built at the site inspection on 17 September 2026. The site has been inspected 7 times since October 2022. The Land Department took 42 site photos at its inspections.
Is Ag Square delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Ag Square?
The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Ag Square?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.