Ag Square construction progress
Ag Square in Dubai Land Residence Complex was registered to complete in September 2026 and is still under construction. At the last site inspection, in September 2026, it was 69% built. The developer is Ag Properties.
69%
Built, at the site inspection of 17 September 2026
2 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- September 2027
- Construction started
- September 2022
- First registered
- October 2022
- Developer
- Ag Properties
- Community
- Dubai Land Residence Complex
- Units
- 372
- Escrow bank
- Emirates NBD
- Name in Arabic
- ايه جي سكوير
- Project number
- 2424
- Site inspections
- 7
Schedule
Ag Square was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.7 points a month. Kept at that rate, the site would reach 100% around September 2027.
Site inspections
17 September 2026
69%+20 pts
9 February 2026
49%+11 pts
21 July 2025
39%+6.1 pts
28 February 2025
32%+8.9 pts
16 October 2024
24%+18 pts
13 November 2023
5.0%+5.0 pts
3 October 2022
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Ag Properties has 4 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Ag Square?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ag Square handover date?
- The registered completion date was September 2026, and the register still lists Ag Square as under construction. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ag Square?
- Ag Square was 69% built at the site inspection on 17 September 2026. The site has been inspected 7 times since October 2022. The Land Department took 42 site photos at its inspections.
- Is Ag Square delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Ag Square?
- The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Ag Square?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralAlso by Ag Properties. 59%, Due October 2026, passed.
- Ag 7evenAlso by Ag Properties. 94%, Due March 2027.
- Ag 9ineAlso by Ag Properties. 38%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Samana Ivy GardensNearby in Dubai Land Residence Complex. 41%.
- A 99Nearby in Dubai Land Residence Complex. 48%, Due October 2026, passed.
- Samana Park MeadowsNearby in Dubai Land Residence Complex. 38%, Due August 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)