Ag 7even construction progress

The registered completion date for Ag 7even in Dubai Land Residence Complex is March 2027. At the last site inspection, in June 2026, it was 94% built. The developer is Ag Properties.

94%

Built, at the site inspection of 18 June 2026

On pace for its date

Registered completion date
March 2027
Finish at recent pace
August 2026
Construction started
March 2023
First registered
May 2023
Developer
Ag Properties
Units
234
Escrow bank
Emirates NBD
Name in Arabic
ايه جي 7سيفين
Project number
2605
Site inspections
8

Schedule

Since October 2025 Ag 7even has added about 3.6 points a month. That puts 100% around August 2026, within three months of its registered completion date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 June 2026

94%+8.6 pts

  • Ag 7even construction site, inspection photo 1, 18 June 2026
  • Ag 7even construction site, inspection photo 2, 18 June 2026
  • Ag 7even construction site, inspection photo 3, 18 June 2026
  • Ag 7even construction site, inspection photo 4, 18 June 2026

12 February 2026

85%+21 pts

  • Ag 7even construction site, inspection photo 1, 12 February 2026
  • Ag 7even construction site, inspection photo 2, 12 February 2026
  • Ag 7even construction site, inspection photo 3, 12 February 2026
  • Ag 7even construction site, inspection photo 4, 12 February 2026

9 October 2025

64%+12 pts

  • Ag 7even construction site, inspection photo 1, 9 October 2025
  • Ag 7even construction site, inspection photo 2, 9 October 2025
  • Ag 7even construction site, inspection photo 3, 9 October 2025
  • Ag 7even construction site, inspection photo 4, 9 October 2025

14 April 2025

52%+11 pts

  • Ag 7even construction site, inspection photo 1, 14 April 2025
  • Ag 7even construction site, inspection photo 2, 14 April 2025
  • Ag 7even construction site, inspection photo 3, 14 April 2025
  • Ag 7even construction site, inspection photo 4, 14 April 2025

7 November 2024

40%+23 pts

  • Ag 7even construction site, inspection photo 1, 7 November 2024
  • Ag 7even construction site, inspection photo 2, 7 November 2024
  • Ag 7even construction site, inspection photo 3, 7 November 2024
  • Ag 7even construction site, inspection photo 4, 7 November 2024

15 March 2024

18%+3.5 pts

  • Ag 7even construction site, inspection photo 1, 15 March 2024
  • Ag 7even construction site, inspection photo 2, 15 March 2024
  • Ag 7even construction site, inspection photo 3, 15 March 2024
  • Ag 7even construction site, inspection photo 4, 15 March 2024

13 November 2023

14%+13 pts

  • Ag 7even construction site, inspection photo 1, 13 November 2023
  • Ag 7even construction site, inspection photo 2, 13 November 2023
  • Ag 7even construction site, inspection photo 3, 13 November 2023
  • Ag 7even construction site, inspection photo 4, 13 November 2023

27 March 2023

1.1%

  • Ag 7even construction site, inspection photo 1, 27 March 2023
  • Ag 7even construction site, inspection photo 2, 27 March 2023
  • Ag 7even construction site, inspection photo 3, 27 March 2023
  • Ag 7even construction site, inspection photo 4, 27 March 2023

All 78 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Ag Properties has 4 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Ag 7even?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Ag 7even handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Ag 7even?
Ag 7even was 94% built at the site inspection on 18 June 2026. The site has been inspected 8 times since March 2023. The Land Department took 78 site photos at its inspections.
Is Ag 7even delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building Ag 7even?
The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Ag 7even?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.