Ag 7even construction progress

Ag 7even in Dubai Land Residence Complex is 94% built at the Land Department inspection of June 2026. Developer Ag Properties. Completion registered for March 2027.

94%

Built, at the Land Department site inspection of 18 June 2026

On pace for its date

Completion date (Land Department)
March 2027
Finish at recent pace
August 2026
Construction started
March 2023
Registered with the Land Department
May 2023
Developer
Ag Properties
Units
234
Escrow bank
Emirates NBD
Name in Arabic
ايه جي 7سيفين
Land Department project number
2605
Land Department site inspections
8

Schedule

Since October 2025 Ag 7even has added about 3.6 points a month. That puts 100% around August 2026, within three months of its registered completion date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

94%+8.6 pts

  • Ag 7even construction site, Land Department inspection photo 1, 18 June 2026
  • Ag 7even construction site, Land Department inspection photo 2, 18 June 2026
  • Ag 7even construction site, Land Department inspection photo 3, 18 June 2026
  • Ag 7even construction site, Land Department inspection photo 4, 18 June 2026

12 February 2026

85%+21 pts

  • Ag 7even construction site, Land Department inspection photo 1, 12 February 2026
  • Ag 7even construction site, Land Department inspection photo 2, 12 February 2026
  • Ag 7even construction site, Land Department inspection photo 3, 12 February 2026
  • Ag 7even construction site, Land Department inspection photo 4, 12 February 2026

9 October 2025

64%+12 pts

  • Ag 7even construction site, Land Department inspection photo 1, 9 October 2025
  • Ag 7even construction site, Land Department inspection photo 2, 9 October 2025
  • Ag 7even construction site, Land Department inspection photo 3, 9 October 2025
  • Ag 7even construction site, Land Department inspection photo 4, 9 October 2025

14 April 2025

52%+11 pts

  • Ag 7even construction site, Land Department inspection photo 1, 14 April 2025
  • Ag 7even construction site, Land Department inspection photo 2, 14 April 2025
  • Ag 7even construction site, Land Department inspection photo 3, 14 April 2025
  • Ag 7even construction site, Land Department inspection photo 4, 14 April 2025

7 November 2024

40%+23 pts

  • Ag 7even construction site, Land Department inspection photo 1, 7 November 2024
  • Ag 7even construction site, Land Department inspection photo 2, 7 November 2024
  • Ag 7even construction site, Land Department inspection photo 3, 7 November 2024
  • Ag 7even construction site, Land Department inspection photo 4, 7 November 2024

15 March 2024

18%+3.5 pts

  • Ag 7even construction site, Land Department inspection photo 1, 15 March 2024
  • Ag 7even construction site, Land Department inspection photo 2, 15 March 2024
  • Ag 7even construction site, Land Department inspection photo 3, 15 March 2024
  • Ag 7even construction site, Land Department inspection photo 4, 15 March 2024

13 November 2023

14%+13 pts

  • Ag 7even construction site, Land Department inspection photo 1, 13 November 2023
  • Ag 7even construction site, Land Department inspection photo 2, 13 November 2023
  • Ag 7even construction site, Land Department inspection photo 3, 13 November 2023
  • Ag 7even construction site, Land Department inspection photo 4, 13 November 2023

27 March 2023

1.1%

  • Ag 7even construction site, Land Department inspection photo 1, 27 March 2023
  • Ag 7even construction site, Land Department inspection photo 2, 27 March 2023
  • Ag 7even construction site, Land Department inspection photo 3, 27 March 2023
  • Ag 7even construction site, Land Department inspection photo 4, 27 March 2023

All 78 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Ag 7even is ahead of that average.

Ag Properties has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Ag 7even?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Ag 7even be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around August 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Ag 7even is built?
94%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 8 times since March 2023.
Is Ag 7even delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building Ag 7even?
The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Ag 7even?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.