Ag 7even construction progress
Ag 7even in Dubai Land Residence Complex is 94% built at the Land Department inspection of June 2026. Developer Ag Properties. Completion registered for March 2027.
94%
Built, at the Land Department site inspection of 18 June 2026
On pace for its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- August 2026
- Construction started
- March 2023
- Registered with the Land Department
- May 2023
- Developer
- Ag Properties
- Community
- Dubai Land Residence Complex
- Units
- 234
- Escrow bank
- Emirates NBD
- Name in Arabic
- ايه جي 7سيفين
- Land Department project number
- 2605
- Land Department site inspections
- 8
Schedule
Since October 2025 Ag 7even has added about 3.6 points a month. That puts 100% around August 2026, within three months of its registered completion date of March 2027.
Site inspections
18 June 2026
94%+8.6 pts
12 February 2026
85%+21 pts
9 October 2025
64%+12 pts
14 April 2025
52%+11 pts
7 November 2024
40%+23 pts
15 March 2024
18%+3.5 pts
13 November 2023
14%+13 pts
27 March 2023
1.1%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Ag 7even is ahead of that average.
Ag Properties has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ag 7even?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Ag 7even be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around August 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ag 7even is built?
- 94%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 8 times since March 2023.
- Is Ag 7even delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building Ag 7even?
- The registered developer is Ag Properties. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Ag 7even?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralAlso by Ag Properties. 59%, Due October 2026.
- Ag SquareAlso by Ag Properties. 69%.
- Ag 9ineAlso by Ag Properties. 38%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Samana Ivy GardensNearby in Dubai Land Residence Complex. 41%.
- A 99Nearby in Dubai Land Residence Complex. 45%, Due October 2026.
- Samana Park MeadowsNearby in Dubai Land Residence Complex. 38%, Due August 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)