Samana Park Meadows construction progress
Samana Park Meadows in Dubai Land Residence Complex is 38% built at the Land Department inspection of October 2026. Developer Samana International Real Estate Development. Completion registered for August 2027.
38%
Built, at the Land Department site inspection of 1 October 2026
Running behind its date
- Completion date (Land Department)
- August 2027
- Finish at recent pace
- September 2028
- Construction started
- August 2024
- Registered with the Land Department
- August 2024
- Community
- Dubai Land Residence Complex
- Units
- 221
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- سمانا بارك ميدوز
- Land Department project number
- 2896
- Land Department site inspections
- 7
Schedule
Between October 2025 and October 2026 the site added about 2.6 points a month. At that rate it would finish around September 2028, more than three months after the August 2027 date registered with the Land Department.
Site inspections
1 October 2026
38%+11 pts
18 June 2026
27%+9.9 pts
3 February 2026
17%+8.8 pts
23 October 2025
8.6%+4.2 pts
16 July 2025
4.4%+2.4 pts
25 December 2024
2.0%+2.0 pts
4 March 2024
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Samana Park Meadows?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Samana Park Meadows be completed?
- The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around September 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Samana Park Meadows is built?
- 38%, measured at the Land Department site inspection on 1 October 2026. The Land Department engineers have inspected the site 7 times since March 2024.
- Is Samana Park Meadows delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Samana Park Meadows?
- The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Park Meadows?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana MykonosAlso by Samana International Real Estate Development. 91%, Due April 2026, passed.
- Samana Mykonos SignatureAlso by Samana International Real Estate Development. 80%, Due April 2026, passed.
- Samana Ivy GardensAlso by Samana International Real Estate Development. 41%.
- Samana Golf ViewsAlso by Samana International Real Estate Development. 56%.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)









.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)