Samana Park Meadows construction progress

The registered completion date for Samana Park Meadows in Dubai Land Residence Complex is August 2027. At the last site inspection, in October 2026, it was 38% built. The developer is Samana International Real Estate Development.

38%

Built, at the site inspection of 1 October 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
September 2028
Construction started
August 2024
First registered
August 2024
Units
221
Escrow bank
First Abu Dhabi Bank
Name in Arabic
سمانا بارك ميدوز
Project number
2896
Site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 2.6 points a month. At that rate it would finish around September 2028, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

38%+11 pts

  • Samana Park Meadows construction site, inspection photo 1, 1 October 2026
  • Samana Park Meadows construction site, inspection photo 2, 1 October 2026
  • Samana Park Meadows construction site, inspection photo 3, 1 October 2026
  • Samana Park Meadows construction site, inspection photo 4, 1 October 2026

18 June 2026

27%+9.9 pts

  • Samana Park Meadows construction site, inspection photo 1, 18 June 2026
  • Samana Park Meadows construction site, inspection photo 2, 18 June 2026
  • Samana Park Meadows construction site, inspection photo 3, 18 June 2026
  • Samana Park Meadows construction site, inspection photo 4, 18 June 2026

3 February 2026

17%+8.8 pts

  • Samana Park Meadows construction site, inspection photo 1, 3 February 2026
  • Samana Park Meadows construction site, inspection photo 2, 3 February 2026
  • Samana Park Meadows construction site, inspection photo 3, 3 February 2026
  • Samana Park Meadows construction site, inspection photo 4, 3 February 2026

23 October 2025

8.6%+4.2 pts

  • Samana Park Meadows construction site, inspection photo 1, 23 October 2025
  • Samana Park Meadows construction site, inspection photo 2, 23 October 2025

16 July 2025

4.4%+2.4 pts

  • Samana Park Meadows construction site, inspection photo 1, 16 July 2025
  • Samana Park Meadows construction site, inspection photo 2, 16 July 2025
  • Samana Park Meadows construction site, inspection photo 3, 16 July 2025
  • Samana Park Meadows construction site, inspection photo 4, 16 July 2025

25 December 2024

2.0%+2.0 pts

  • Samana Park Meadows construction site, inspection photo 1, 25 December 2024
  • Samana Park Meadows construction site, inspection photo 2, 25 December 2024
  • Samana Park Meadows construction site, inspection photo 3, 25 December 2024

4 March 2024

0%

  • Samana Park Meadows construction site, inspection photo 1, 4 March 2024
  • Samana Park Meadows construction site, inspection photo 2, 4 March 2024
  • Samana Park Meadows construction site, inspection photo 3, 4 March 2024

All 32 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Samana International Real Estate Development has 14 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Samana Park Meadows?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Samana Park Meadows handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Samana Park Meadows?
Samana Park Meadows was 38% built at the site inspection on 1 October 2026. The site has been inspected 7 times since March 2024. The Land Department took 32 site photos at its inspections.
Is Samana Park Meadows delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Samana Park Meadows?
The registered developer is Samana International Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Park Meadows?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.