32 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Samana Park Meadows was built on the day of each visit.

1 October 202638% built

18 June 202627% built

3 February 202617% built

23 October 20258.6% built

16 July 20254.4% built

25 December 20242.0% built

4 March 20240% built

Back to Samana Park Meadows construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.