Skip to content

Off-plan projects in Dubai Harbour

11 projects in Dubai Harbour are under construction. On average they are 36% built. The next one due is Address The Bay, in December 2026.

Questions

How many off-plan projects are under construction in Dubai Harbour?

11 projects are under construction in Dubai Harbour, 36% built on average at the latest site inspections.

Which Dubai Harbour projects are due to finish next?

By registered completion date: Address The Bay (December 2026, 70% built), Damac Bay (January 2027, 34% built) and Dubai Harbour Residences (Area 3) (January 2028, 35% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.

How many Dubai Harbour projects are past their completion date?

None. Every project here with a registered completion date is still inside it.

Which developers are building in Dubai Harbour?

The developers with the most projects here are Emaar Development (4), Harbour One Investment (2) and Sobha (2), out of 6 building in Dubai Harbour.

Reading these figures

Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.

What happens at handover and how to snag a new home cover the steps after 100%.

Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.