The Valley - Rivana construction progress

The Valley - Rivana in Al Yufrah 1 is 94% built at the Land Department inspection of August 2026. Developer Emaar Development. Completion registered for March 2027.

94%

Built, at the Land Department site inspection of 5 August 2026

On pace for its date

Completion date (Land Department)
March 2027
Finish at recent pace
November 2026
Construction started
September 2023
Registered with the Land Department
June 2023
Community
Al Yufrah 1
Units
486
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا فالي - ريفانا
Land Department project number
2704
Land Department site inspections
8

Schedule

Since November 2025 The Valley - Rivana has added about 1.8 points a month. That puts 100% around November 2026, within three months of its registered completion date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 August 2026

94%+4.1 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 5 August 2026
  • The Valley - Rivana construction site, Land Department inspection photo 2, 5 August 2026
  • The Valley - Rivana construction site, Land Department inspection photo 3, 5 August 2026
  • The Valley - Rivana construction site, Land Department inspection photo 4, 5 August 2026

22 April 2026

90%+12 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 22 April 2026
  • The Valley - Rivana construction site, Land Department inspection photo 2, 22 April 2026
  • The Valley - Rivana construction site, Land Department inspection photo 3, 22 April 2026
  • The Valley - Rivana construction site, Land Department inspection photo 4, 22 April 2026

6 November 2025

77%+13 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 6 November 2025
  • The Valley - Rivana construction site, Land Department inspection photo 2, 6 November 2025
  • The Valley - Rivana construction site, Land Department inspection photo 3, 6 November 2025
  • The Valley - Rivana construction site, Land Department inspection photo 4, 6 November 2025

4 July 2025

64%+21 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 4 July 2025
  • The Valley - Rivana construction site, Land Department inspection photo 2, 4 July 2025
  • The Valley - Rivana construction site, Land Department inspection photo 3, 4 July 2025
  • The Valley - Rivana construction site, Land Department inspection photo 4, 4 July 2025

10 February 2025

43%+21 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 10 February 2025
  • The Valley - Rivana construction site, Land Department inspection photo 2, 10 February 2025
  • The Valley - Rivana construction site, Land Department inspection photo 3, 10 February 2025
  • The Valley - Rivana construction site, Land Department inspection photo 4, 10 February 2025

2 October 2024

22%+19 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 2 October 2024
  • The Valley - Rivana construction site, Land Department inspection photo 2, 2 October 2024
  • The Valley - Rivana construction site, Land Department inspection photo 3, 2 October 2024
  • The Valley - Rivana construction site, Land Department inspection photo 4, 2 October 2024

22 March 2024

3.8%+3.8 pts

  • The Valley - Rivana construction site, Land Department inspection photo 1, 22 March 2024
  • The Valley - Rivana construction site, Land Department inspection photo 2, 22 March 2024
  • The Valley - Rivana construction site, Land Department inspection photo 3, 22 March 2024
  • The Valley - Rivana construction site, Land Department inspection photo 4, 22 March 2024

16 June 2023

0%

  • The Valley - Rivana construction site, Land Department inspection photo 1, 16 June 2023
  • The Valley - Rivana construction site, Land Department inspection photo 2, 16 June 2023
  • The Valley - Rivana construction site, Land Department inspection photo 3, 16 June 2023

All 67 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 37% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Rivana?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Valley - Rivana be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Valley - Rivana is built?
94%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 8 times since June 2023.
Is The Valley - Rivana delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building The Valley - Rivana?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Rivana?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.