The Valley - Rivana construction progress

The registered completion date for The Valley - Rivana in Al Yufrah 1 is March 2027. At the last site inspection, in October 2026, it was 95% built. The developer is Emaar Development.

95%

Built, at the site inspection of 28 October 2026

On pace for its date

Registered completion date
March 2027
Finish at recent pace
January 2027
Construction started
September 2023
First registered
June 2023
Community
Al Yufrah 1
Units
486
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا فالي - ريفانا
Project number
2704
Site inspections
9

Schedule

Since November 2025 The Valley - Rivana has added about 1.5 points a month. That puts 100% around January 2027, within three months of its registered completion date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

95%+1.4 pts

  • The Valley - Rivana construction site, inspection photo 1, 28 October 2026
  • The Valley - Rivana construction site, inspection photo 2, 28 October 2026
  • The Valley - Rivana construction site, inspection photo 3, 28 October 2026
  • The Valley - Rivana construction site, inspection photo 4, 28 October 2026

5 August 2026

94%+4.1 pts

  • The Valley - Rivana construction site, inspection photo 1, 5 August 2026
  • The Valley - Rivana construction site, inspection photo 2, 5 August 2026
  • The Valley - Rivana construction site, inspection photo 3, 5 August 2026
  • The Valley - Rivana construction site, inspection photo 4, 5 August 2026

22 April 2026

90%+12 pts

  • The Valley - Rivana construction site, inspection photo 1, 22 April 2026
  • The Valley - Rivana construction site, inspection photo 2, 22 April 2026
  • The Valley - Rivana construction site, inspection photo 3, 22 April 2026
  • The Valley - Rivana construction site, inspection photo 4, 22 April 2026

6 November 2025

77%+13 pts

  • The Valley - Rivana construction site, inspection photo 1, 6 November 2025
  • The Valley - Rivana construction site, inspection photo 2, 6 November 2025
  • The Valley - Rivana construction site, inspection photo 3, 6 November 2025
  • The Valley - Rivana construction site, inspection photo 4, 6 November 2025

4 July 2025

64%+21 pts

  • The Valley - Rivana construction site, inspection photo 1, 4 July 2025
  • The Valley - Rivana construction site, inspection photo 2, 4 July 2025
  • The Valley - Rivana construction site, inspection photo 3, 4 July 2025
  • The Valley - Rivana construction site, inspection photo 4, 4 July 2025

10 February 2025

43%+21 pts

  • The Valley - Rivana construction site, inspection photo 1, 10 February 2025
  • The Valley - Rivana construction site, inspection photo 2, 10 February 2025
  • The Valley - Rivana construction site, inspection photo 3, 10 February 2025
  • The Valley - Rivana construction site, inspection photo 4, 10 February 2025

2 October 2024

22%+19 pts

  • The Valley - Rivana construction site, inspection photo 1, 2 October 2024
  • The Valley - Rivana construction site, inspection photo 2, 2 October 2024
  • The Valley - Rivana construction site, inspection photo 3, 2 October 2024
  • The Valley - Rivana construction site, inspection photo 4, 2 October 2024

22 March 2024

3.8%+3.8 pts

  • The Valley - Rivana construction site, inspection photo 1, 22 March 2024
  • The Valley - Rivana construction site, inspection photo 2, 22 March 2024
  • The Valley - Rivana construction site, inspection photo 3, 22 March 2024
  • The Valley - Rivana construction site, inspection photo 4, 22 March 2024

16 June 2023

0%

  • The Valley - Rivana construction site, inspection photo 1, 16 June 2023
  • The Valley - Rivana construction site, inspection photo 2, 16 June 2023
  • The Valley - Rivana construction site, inspection photo 3, 16 June 2023

All 76 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Rivana?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Rivana handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Rivana?
The Valley - Rivana was 95% built at the site inspection on 28 October 2026. The site has been inspected 9 times since June 2023. The Land Department took 76 site photos at its inspections.
Is The Valley - Rivana delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building The Valley - Rivana?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Rivana?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.