The Valley - Rivana construction progress
The Valley - Rivana in Al Yufrah 1 is 94% built at the Land Department inspection of August 2026. Developer Emaar Development. Completion registered for March 2027.
94%
Built, at the Land Department site inspection of 5 August 2026
On pace for its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- November 2026
- Construction started
- September 2023
- Registered with the Land Department
- June 2023
- Developer
- Emaar Development
- Community
- Al Yufrah 1
- Units
- 486
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ذا فالي - ريفانا
- Land Department project number
- 2704
- Land Department site inspections
- 8
Schedule
Since November 2025 The Valley - Rivana has added about 1.8 points a month. That puts 100% around November 2026, within three months of its registered completion date of March 2027.
Site inspections
5 August 2026
94%+4.1 pts
22 April 2026
90%+12 pts
6 November 2025
77%+13 pts
4 July 2025
64%+21 pts
10 February 2025
43%+21 pts
2 October 2024
22%+19 pts
22 March 2024
3.8%+3.8 pts
16 June 2023
0%
Context
Al Yufrah 1 has 17 projects under construction, 37% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Valley - Rivana?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Valley - Rivana be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Valley - Rivana is built?
- 94%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 8 times since June 2023.
- Is The Valley - Rivana delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building The Valley - Rivana?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for The Valley - Rivana?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Elwood EstatesNearby in Al Yufrah 1. 14%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)