Seapoint construction photos

57 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Seapoint was built on the day of each visit.

24 June 202637% built

4 February 202625% built

3 October 202516% built

23 May 20259.8% built

29 January 20256.6% built

10 October 20245.5% built

5 June 20240.4% built

8 November 20230.2% built

7 April 20230% built

Back to Seapoint construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.