Damac Bay construction progress

The registered completion date for Damac Bay in Dubai Harbour is January 2027. At the last site inspection, in August 2026, it was 34% built. The developer is Damac J R Two Investment.

34%

Built, at the site inspection of 18 August 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
June 2031
Construction started
April 2023
First registered
January 2023
Developer
Damac J R Two Investment
Community
Dubai Harbour
Units
1,087
Escrow bank
Emirates NBD
Name in Arabic
داماك باي
Project number
2559
Site inspections
10

Schedule

Between December 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around June 2031, more than three months after its registered date of January 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 August 2026

34%+4.9 pts

  • Damac Bay construction site, inspection photo 1, 18 August 2026
  • Damac Bay construction site, inspection photo 2, 18 August 2026
  • Damac Bay construction site, inspection photo 3, 18 August 2026
  • Damac Bay construction site, inspection photo 4, 18 August 2026

17 April 2026

29%+4.4 pts

  • Damac Bay construction site, inspection photo 1, 17 April 2026
  • Damac Bay construction site, inspection photo 2, 17 April 2026
  • Damac Bay construction site, inspection photo 3, 17 April 2026
  • Damac Bay construction site, inspection photo 4, 17 April 2026

15 December 2025

25%+8.2 pts

  • Damac Bay construction site, inspection photo 1, 15 December 2025
  • Damac Bay construction site, inspection photo 2, 15 December 2025
  • Damac Bay construction site, inspection photo 3, 15 December 2025
  • Damac Bay construction site, inspection photo 4, 15 December 2025

15 April 2025

16%+7.5 pts

  • Damac Bay construction site, inspection photo 1, 15 April 2025
  • Damac Bay construction site, inspection photo 2, 15 April 2025
  • Damac Bay construction site, inspection photo 3, 15 April 2025
  • Damac Bay construction site, inspection photo 4, 15 April 2025

11 December 2024

8.8%+2.9 pts

  • Damac Bay construction site, inspection photo 1, 11 December 2024
  • Damac Bay construction site, inspection photo 2, 11 December 2024
  • Damac Bay construction site, inspection photo 3, 11 December 2024
  • Damac Bay construction site, inspection photo 4, 11 December 2024

5 July 2024

5.9%+1.7 pts

  • Damac Bay construction site, inspection photo 1, 5 July 2024
  • Damac Bay construction site, inspection photo 2, 5 July 2024
  • Damac Bay construction site, inspection photo 3, 5 July 2024

13 March 2024

4.2%+1.7 pts

  • Damac Bay construction site, inspection photo 1, 13 March 2024
  • Damac Bay construction site, inspection photo 2, 13 March 2024
  • Damac Bay construction site, inspection photo 3, 13 March 2024
  • Damac Bay construction site, inspection photo 4, 13 March 2024

5 December 2023

2.5%+2.4 pts

  • Damac Bay construction site, inspection photo 1, 5 December 2023
  • Damac Bay construction site, inspection photo 2, 5 December 2023
  • Damac Bay construction site, inspection photo 3, 5 December 2023
  • Damac Bay construction site, inspection photo 4, 5 December 2023

7 September 2023

0%+0.0 pts

  • Damac Bay construction site, inspection photo 1, 7 September 2023
  • Damac Bay construction site, inspection photo 2, 7 September 2023
  • Damac Bay construction site, inspection photo 3, 7 September 2023

18 January 2023

0%

  • Damac Bay construction site, inspection photo 1, 18 January 2023
  • Damac Bay construction site, inspection photo 2, 18 January 2023
  • Damac Bay construction site, inspection photo 3, 18 January 2023

All 57 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 36% built on average.

Own a unit in Damac Bay?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac Bay handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac Bay?
Damac Bay was 34% built at the site inspection on 18 August 2026. The site has been inspected 10 times since January 2023. The Land Department took 57 site photos at its inspections.
Is Damac Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Damac Bay?
The registered developer is Damac J R Two Investment.
Which bank holds the escrow account for Damac Bay?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.