Damac Bay construction progress
Damac Bay in Dubai Harbour is 34% built at the Land Department inspection of August 2026. Developer Damac J R Two Investment. Completion registered for January 2027.
34%
Built, at the Land Department site inspection of 18 August 2026
Running behind its date
- Completion date (Land Department)
- January 2027
- Finish at recent pace
- June 2031
- Construction started
- April 2023
- Registered with the Land Department
- January 2023
- Developer
- Damac J R Two Investment
- Community
- Dubai Harbour
- Units
- 1,087
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك باي
- Land Department project number
- 2559
- Land Department site inspections
- 10
Schedule
Between December 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around June 2031, more than three months after the January 2027 date registered with the Land Department.
Site inspections
18 August 2026
34%+4.9 pts
17 April 2026
29%+4.4 pts
15 December 2025
25%+8.2 pts
15 April 2025
16%+7.5 pts
11 December 2024
8.8%+2.9 pts
5 July 2024
5.9%+1.7 pts
13 March 2024
4.2%+1.7 pts
5 December 2023
2.5%+2.4 pts
7 September 2023
0%+0.0 pts
18 January 2023
0%
Context
Dubai Harbour has 11 projects under construction, 35% built on average. Damac Bay is behind that average.
Own a unit in Damac Bay?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Damac Bay be completed?
- The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around June 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Damac Bay is built?
- 34%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 10 times since January 2023.
- Is Damac Bay delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Damac Bay?
- The registered developer is Damac J R Two Investment.
- Which bank holds the escrow account for Damac Bay?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Address The BayNearby in Dubai Harbour. 70%, Due December 2026.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 37%, Due April 2028.
- SeapointNearby in Dubai Harbour. 37%, Due March 2028.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.