Damac Bay construction progress

Damac Bay in Dubai Harbour is 34% built at the Land Department inspection of August 2026. Developer Damac J R Two Investment. Completion registered for January 2027.

34%

Built, at the Land Department site inspection of 18 August 2026

Running behind its date

Completion date (Land Department)
January 2027
Finish at recent pace
June 2031
Construction started
April 2023
Registered with the Land Department
January 2023
Developer
Damac J R Two Investment
Community
Dubai Harbour
Units
1,087
Escrow bank
Emirates NBD
Name in Arabic
داماك باي
Land Department project number
2559
Land Department site inspections
10

Schedule

Between December 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around June 2031, more than three months after the January 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 August 2026

34%+4.9 pts

  • Damac Bay construction site, Land Department inspection photo 1, 18 August 2026
  • Damac Bay construction site, Land Department inspection photo 2, 18 August 2026
  • Damac Bay construction site, Land Department inspection photo 3, 18 August 2026
  • Damac Bay construction site, Land Department inspection photo 4, 18 August 2026

17 April 2026

29%+4.4 pts

  • Damac Bay construction site, Land Department inspection photo 1, 17 April 2026
  • Damac Bay construction site, Land Department inspection photo 2, 17 April 2026
  • Damac Bay construction site, Land Department inspection photo 3, 17 April 2026
  • Damac Bay construction site, Land Department inspection photo 4, 17 April 2026

15 December 2025

25%+8.2 pts

  • Damac Bay construction site, Land Department inspection photo 1, 15 December 2025
  • Damac Bay construction site, Land Department inspection photo 2, 15 December 2025
  • Damac Bay construction site, Land Department inspection photo 3, 15 December 2025
  • Damac Bay construction site, Land Department inspection photo 4, 15 December 2025

15 April 2025

16%+7.5 pts

  • Damac Bay construction site, Land Department inspection photo 1, 15 April 2025
  • Damac Bay construction site, Land Department inspection photo 2, 15 April 2025
  • Damac Bay construction site, Land Department inspection photo 3, 15 April 2025
  • Damac Bay construction site, Land Department inspection photo 4, 15 April 2025

11 December 2024

8.8%+2.9 pts

  • Damac Bay construction site, Land Department inspection photo 1, 11 December 2024
  • Damac Bay construction site, Land Department inspection photo 2, 11 December 2024
  • Damac Bay construction site, Land Department inspection photo 3, 11 December 2024
  • Damac Bay construction site, Land Department inspection photo 4, 11 December 2024

5 July 2024

5.9%+1.7 pts

  • Damac Bay construction site, Land Department inspection photo 1, 5 July 2024
  • Damac Bay construction site, Land Department inspection photo 2, 5 July 2024
  • Damac Bay construction site, Land Department inspection photo 3, 5 July 2024

13 March 2024

4.2%+1.7 pts

  • Damac Bay construction site, Land Department inspection photo 1, 13 March 2024
  • Damac Bay construction site, Land Department inspection photo 2, 13 March 2024
  • Damac Bay construction site, Land Department inspection photo 3, 13 March 2024
  • Damac Bay construction site, Land Department inspection photo 4, 13 March 2024

5 December 2023

2.5%+2.4 pts

  • Damac Bay construction site, Land Department inspection photo 1, 5 December 2023
  • Damac Bay construction site, Land Department inspection photo 2, 5 December 2023
  • Damac Bay construction site, Land Department inspection photo 3, 5 December 2023
  • Damac Bay construction site, Land Department inspection photo 4, 5 December 2023

7 September 2023

0%+0.0 pts

  • Damac Bay construction site, Land Department inspection photo 1, 7 September 2023
  • Damac Bay construction site, Land Department inspection photo 2, 7 September 2023
  • Damac Bay construction site, Land Department inspection photo 3, 7 September 2023

18 January 2023

0%

  • Damac Bay construction site, Land Department inspection photo 1, 18 January 2023
  • Damac Bay construction site, Land Department inspection photo 2, 18 January 2023
  • Damac Bay construction site, Land Department inspection photo 3, 18 January 2023

All 57 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 35% built on average. Damac Bay is behind that average.

Own a unit in Damac Bay?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Damac Bay be completed?
The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around June 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Bay is built?
34%, measured at the Land Department site inspection on 18 August 2026. The Land Department engineers have inspected the site 10 times since January 2023.
Is Damac Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Damac Bay?
The registered developer is Damac J R Two Investment.
Which bank holds the escrow account for Damac Bay?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.