Damac Bay construction progress
The registered completion date for Damac Bay in Dubai Harbour is January 2027. At the last site inspection, in August 2026, it was 34% built. The developer is Damac J R Two Investment.
34%
Built, at the site inspection of 18 August 2026
Running behind its date
- Registered completion date
- January 2027
- Finish at recent pace
- June 2031
- Construction started
- April 2023
- First registered
- January 2023
- Developer
- Damac J R Two Investment
- Community
- Dubai Harbour
- Units
- 1,087
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك باي
- Project number
- 2559
- Site inspections
- 10
Schedule
Between December 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around June 2031, more than three months after its registered date of January 2027.
Site inspections
18 August 2026
34%+4.9 pts
17 April 2026
29%+4.4 pts
15 December 2025
25%+8.2 pts
15 April 2025
16%+7.5 pts
11 December 2024
8.8%+2.9 pts
5 July 2024
5.9%+1.7 pts
13 March 2024
4.2%+1.7 pts
5 December 2023
2.5%+2.4 pts
7 September 2023
0%+0.0 pts
18 January 2023
0%
Context
Dubai Harbour has 11 projects under construction, 36% built on average.
Own a unit in Damac Bay?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac Bay handover date?
- The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Damac Bay?
- Damac Bay was 34% built at the site inspection on 18 August 2026. The site has been inspected 10 times since January 2023. The Land Department took 57 site photos at its inspections.
- Is Damac Bay delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Damac Bay?
- The registered developer is Damac J R Two Investment.
- Which bank holds the escrow account for Damac Bay?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Address The BayNearby in Dubai Harbour. 70%, Due December 2026.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 45%, Due April 2028.
- SeapointNearby in Dubai Harbour. 37%, Due March 2028.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)