Sobha Seahaven Tower B & C construction progress
Sobha Seahaven Tower B & C in Dubai Harbour is 40% built at the Land Department inspection of September 2026. Developer Sobha. Completion registered for October 2028.
40%
Built, at the Land Department site inspection of 18 September 2026
Running behind its date
- Completion date (Land Department)
- October 2028
- Finish at recent pace
- March 2029
- Construction started
- October 2023
- Registered with the Land Department
- January 2024
- Developer
- Sobha
- Community
- Dubai Harbour
- Units
- 451
- Escrow bank
- Bank of Baroda
- Name in Arabic
- شوبا سيهيفين البرج ب و سي
- Land Department project number
- 2762
- Land Department site inspections
- 7
Schedule
Between November 2025 and September 2026 the site added about 2.0 points a month. At that rate it would finish around March 2029, more than three months after the October 2028 date registered with the Land Department.
Site inspections
18 September 2026
40%+8.0 pts
11 June 2026
32%+5.3 pts
17 March 2026
27%+6.9 pts
17 November 2025
20%+4.4 pts
12 August 2025
16%+9.1 pts
23 December 2024
6.6%+6.6 pts
24 October 2023
0%
Context
Dubai Harbour has 11 projects under construction, 35% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Seahaven Tower B & C?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Sobha Seahaven Tower B & C be completed?
- The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sobha Seahaven Tower B & C is built?
- 40%, measured at the Land Department site inspection on 18 September 2026. The Land Department engineers have inspected the site 7 times since October 2023.
- Is Sobha Seahaven Tower B & C delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Sobha Seahaven Tower B & C?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Seahaven Tower B & C?
- Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 37%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vistas HeightsAlso by Sobha. 92%.
- 330 Riverside CrescentAlso by Sobha. 60%.
- Address The BayNearby in Dubai Harbour. 70%, Due December 2026.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- SeapointNearby in Dubai Harbour. 37%, Due March 2028.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.