Sobha Seahaven Tower B & C construction progress

Sobha Seahaven Tower B & C in Dubai Harbour is 40% built at the Land Department inspection of September 2026. Developer Sobha. Completion registered for October 2028.

40%

Built, at the Land Department site inspection of 18 September 2026

Running behind its date

Completion date (Land Department)
October 2028
Finish at recent pace
March 2029
Construction started
October 2023
Registered with the Land Department
January 2024
Developer
Sobha
Community
Dubai Harbour
Units
451
Escrow bank
Bank of Baroda
Name in Arabic
شوبا سيهيفين البرج ب و سي
Land Department project number
2762
Land Department site inspections
7

Schedule

Between November 2025 and September 2026 the site added about 2.0 points a month. At that rate it would finish around March 2029, more than three months after the October 2028 date registered with the Land Department.

0%25%50%75%100%20242025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 September 2026

40%+8.0 pts

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 18 September 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 18 September 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 3, 18 September 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 4, 18 September 2026

11 June 2026

32%+5.3 pts

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 11 June 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 11 June 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 3, 11 June 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 4, 11 June 2026

17 March 2026

27%+6.9 pts

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 17 March 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 17 March 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 3, 17 March 2026
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 4, 17 March 2026

17 November 2025

20%+4.4 pts

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 17 November 2025
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 17 November 2025
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 3, 17 November 2025
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 4, 17 November 2025

12 August 2025

16%+9.1 pts

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 12 August 2025
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 12 August 2025
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 3, 12 August 2025
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 4, 12 August 2025

23 December 2024

6.6%+6.6 pts

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 23 December 2024
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 23 December 2024
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 3, 23 December 2024
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 4, 23 December 2024

24 October 2023

0%

  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 1, 24 October 2023
  • Sobha Seahaven Tower B & C construction site, Land Department inspection photo 2, 24 October 2023

All 43 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 35% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Seahaven Tower B & C?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sobha Seahaven Tower B & C be completed?
The completion date registered with the Dubai Land Department is October 2028. At the pace of its recent inspections the site would reach 100% around March 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sobha Seahaven Tower B & C is built?
40%, measured at the Land Department site inspection on 18 September 2026. The Land Department engineers have inspected the site 7 times since October 2023.
Is Sobha Seahaven Tower B & C delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
Who is building Sobha Seahaven Tower B & C?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Seahaven Tower B & C?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.