Sobha Seahaven Tower A construction progress
The registered completion date for Sobha Seahaven Tower A in Dubai Harbour is April 2028. At the last site inspection, in November 2026, it was 45% built. The developer is Sobha.
45%
Built, at the site inspection of 9 November 2026
Running behind its date
- Registered completion date
- April 2028
- Finish at recent pace
- April 2029
- Construction started
- July 2023
- First registered
- April 2023
- Developer
- Sobha
- Community
- Dubai Harbour
- Units
- 333
- Escrow bank
- Emirates NBD
- Name in Arabic
- شوبا سيهافين البرج أ
- Project number
- 2550
- Site inspections
- 7
Schedule
Between January 2026 and November 2026 the site added about 1.9 points a month. At that rate it would finish around April 2029, more than three months after its registered date of April 2028.
Site inspections
9 November 2026
45%+8.2 pts
6 August 2026
37%+6.1 pts
27 April 2026
31%+4.3 pts
15 January 2026
27%+4.2 pts
12 September 2025
22%+11 pts
17 October 2024
11%+11 pts
9 February 2023
0%
Context
Dubai Harbour has 11 projects under construction, 36% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Seahaven Tower A?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sobha Seahaven Tower A handover date?
- The registered completion date is April 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sobha Seahaven Tower A?
- Sobha Seahaven Tower A was 45% built at the site inspection on 9 November 2026. The site has been inspected 7 times since February 2023. The Land Department took 44 site photos at its inspections.
- Is Sobha Seahaven Tower A delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
- Who is building Sobha Seahaven Tower A?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Seahaven Tower A?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- 330 Riverside CrescentAlso by Sobha. 68%.
- Address The BayNearby in Dubai Harbour. 70%, Due December 2026.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- SeapointNearby in Dubai Harbour. 37%, Due March 2028.
- Damac Bay 2Nearby in Dubai Harbour. 30%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)









.jpeg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)