Sobha Seahaven Tower A construction progress

Sobha Seahaven Tower A in Dubai Harbour is 37% built at the Land Department inspection of August 2026. Developer Sobha. Completion registered for April 2028.

37%

Built, at the Land Department site inspection of 6 August 2026

Running behind its date

Completion date (Land Department)
April 2028
Finish at recent pace
June 2030
Construction started
July 2023
Registered with the Land Department
April 2023
Developer
Sobha
Community
Dubai Harbour
Units
333
Escrow bank
Emirates NBD
Name in Arabic
شوبا سيهافين البرج أ
Land Department project number
2550
Land Department site inspections
6

Schedule

Between September 2025 and August 2026 the site added about 1.4 points a month. At that rate it would finish around June 2030, more than three months after the April 2028 date registered with the Land Department.

0%25%50%75%100%20242025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 August 2026

37%+6.1 pts

  • Sobha Seahaven Tower A construction site, Land Department inspection photo 1, 6 August 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 2, 6 August 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 3, 6 August 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 4, 6 August 2026

27 April 2026

31%+4.3 pts

  • Sobha Seahaven Tower A construction site, Land Department inspection photo 1, 27 April 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 2, 27 April 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 3, 27 April 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 4, 27 April 2026

15 January 2026

27%+4.2 pts

  • Sobha Seahaven Tower A construction site, Land Department inspection photo 1, 15 January 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 2, 15 January 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 3, 15 January 2026
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 4, 15 January 2026

12 September 2025

22%+11 pts

  • Sobha Seahaven Tower A construction site, Land Department inspection photo 1, 12 September 2025
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 2, 12 September 2025
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 3, 12 September 2025
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 4, 12 September 2025

17 October 2024

11%+11 pts

  • Sobha Seahaven Tower A construction site, Land Department inspection photo 1, 17 October 2024
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 2, 17 October 2024
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 3, 17 October 2024
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 4, 17 October 2024

9 February 2023

0%

  • Sobha Seahaven Tower A construction site, Land Department inspection photo 1, 9 February 2023
  • Sobha Seahaven Tower A construction site, Land Department inspection photo 2, 9 February 2023

All 34 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 35% built on average. Sobha Seahaven Tower A is ahead of that average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Seahaven Tower A?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Sobha Seahaven Tower A be completed?
The completion date registered with the Dubai Land Department is April 2028. At the pace of its recent inspections the site would reach 100% around June 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sobha Seahaven Tower A is built?
37%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 6 times since February 2023.
Is Sobha Seahaven Tower A delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
Who is building Sobha Seahaven Tower A?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Seahaven Tower A?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.