Bayview construction photos

61 photos taken by Dubai Land Department engineers at 10 site inspections, newest first. The percentage is how much of Bayview was built on the day of each visit.

14 September 202663% built

30 June 202649% built

2 February 202635% built

3 October 202522% built

19 June 202518% built

9 March 202514% built

8 October 20249.1% built

26 April 20242.9% built

25 December 20230% built

8 May 20230% built

Back to Bayview construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.