Address The Bay construction photos
61 photos taken by Dubai Land Department engineers at 11 site inspections, newest first. The percentage is how much of Address The Bay was built on the day of each visit.
15 July 202670% built
17 March 202667% built
4 December 202549% built
10 July 202539% built
28 April 202530% built
16 December 202421% built
23 August 202412% built
21 March 20246.9% built
9 October 20231.4% built
20 June 20230% built
6 March 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.