The Bristol Emaar Beachfront construction progress

The registered completion date for The Bristol Emaar Beachfront in Dubai Harbour is September 2029. At the last site inspection, in June 2026, it was 5.8% built. The developer is Emaar Development.

5.8%

Built, at the site inspection of 23 June 2026

Running behind its date

Registered completion date
September 2029
Finish at recent pace
September 2041
Construction started
May 2025
First registered
December 2024
Community
Dubai Harbour
Units
229
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا بريستول اعمار بيتشفرونت
Project number
3439
Site inspections
5

Schedule

Between July 2025 and June 2026 the site added about 0.5 points a month. At that rate it would finish around September 2041, more than three months after its registered date of September 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 June 2026

5.8%+0.7 pts

  • The Bristol Emaar Beachfront construction site, inspection photo 1, 23 June 2026
  • The Bristol Emaar Beachfront construction site, inspection photo 2, 23 June 2026

17 March 2026

5.1%+4.5 pts

  • The Bristol Emaar Beachfront construction site, inspection photo 1, 17 March 2026
  • The Bristol Emaar Beachfront construction site, inspection photo 2, 17 March 2026
  • The Bristol Emaar Beachfront construction site, inspection photo 3, 17 March 2026
  • The Bristol Emaar Beachfront construction site, inspection photo 4, 17 March 2026

4 December 2025

0.6%+0.5 pts

  • The Bristol Emaar Beachfront construction site, inspection photo 1, 4 December 2025
  • The Bristol Emaar Beachfront construction site, inspection photo 2, 4 December 2025
  • The Bristol Emaar Beachfront construction site, inspection photo 3, 4 December 2025

17 July 2025

0.1%+0.1 pts

  • The Bristol Emaar Beachfront construction site, inspection photo 1, 17 July 2025
  • The Bristol Emaar Beachfront construction site, inspection photo 2, 17 July 2025
  • The Bristol Emaar Beachfront construction site, inspection photo 3, 17 July 2025
  • The Bristol Emaar Beachfront construction site, inspection photo 4, 17 July 2025

29 November 2024

0%

  • The Bristol Emaar Beachfront construction site, inspection photo 1, 29 November 2024
  • The Bristol Emaar Beachfront construction site, inspection photo 2, 29 November 2024

All 17 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 36% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Bristol Emaar Beachfront?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Bristol Emaar Beachfront handover date?
The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2041. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Bristol Emaar Beachfront?
The Bristol Emaar Beachfront was 5.8% built at the site inspection on 23 June 2026. The site has been inspected 5 times since November 2024. The Land Department took 17 site photos at its inspections.
Is The Bristol Emaar Beachfront delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building The Bristol Emaar Beachfront?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Bristol Emaar Beachfront?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.