The Bristol Emaar Beachfront construction progress

The Bristol Emaar Beachfront in Dubai Harbour is 5.8% built at the Land Department inspection of June 2026. Developer Emaar Development. Completion registered for September 2029.

5.8%

Built, at the Land Department site inspection of 23 June 2026

Running behind its date

Completion date (Land Department)
September 2029
Finish at recent pace
September 2041
Construction started
May 2025
Registered with the Land Department
December 2024
Community
Dubai Harbour
Units
229
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا بريستول اعمار بيتشفرونت
Land Department project number
3439
Land Department site inspections
5

Schedule

Between July 2025 and June 2026 the site added about 0.5 points a month. At that rate it would finish around September 2041, more than three months after the September 2029 date registered with the Land Department.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 June 2026

5.8%+0.7 pts

  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 1, 23 June 2026
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 2, 23 June 2026

17 March 2026

5.1%+4.5 pts

  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 1, 17 March 2026
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 2, 17 March 2026
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 3, 17 March 2026
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 4, 17 March 2026

4 December 2025

0.6%+0.5 pts

  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 1, 4 December 2025
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 2, 4 December 2025
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 3, 4 December 2025

17 July 2025

0.1%+0.1 pts

  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 1, 17 July 2025
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 2, 17 July 2025
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 3, 17 July 2025
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 4, 17 July 2025

29 November 2024

0%

  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 1, 29 November 2024
  • The Bristol Emaar Beachfront construction site, Land Department inspection photo 2, 29 November 2024

All 17 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 35% built on average. The Bristol Emaar Beachfront is behind that average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Bristol Emaar Beachfront?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Bristol Emaar Beachfront be completed?
The completion date registered with the Dubai Land Department is September 2029. At the pace of its recent inspections the site would reach 100% around September 2041. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Bristol Emaar Beachfront is built?
5.8%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 5 times since November 2024.
Is The Bristol Emaar Beachfront delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building The Bristol Emaar Beachfront?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Bristol Emaar Beachfront?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.