Dubai Harbour Residences (Area 1) construction progress
Dubai Harbour Residences (Area 1) in Dubai Harbour is 30% built at the Land Department inspection of August 2026. Developer Harbour One Investment. Completion registered for January 2028.
30%
Built, at the Land Department site inspection of 11 August 2026
On pace for its date
- Completion date (Land Department)
- January 2028
- Finish at recent pace
- February 2028
- Construction started
- February 2025
- Registered with the Land Department
- July 2024
- Developer
- Harbour One Investment
- Community
- Dubai Harbour
- Units
- 217
- Escrow bank
- Emirates NBD
- Name in Arabic
- دبي هاربور رزيدنسز (المنطقة 1)
- Land Department project number
- 3133
- Land Department site inspections
- 4
Schedule
Since April 2026 Dubai Harbour Residences (Area 1) has added about 3.9 points a month. That puts 100% around February 2028, within three months of its registered completion date of January 2028.
Site inspections
11 August 2026
30%+14 pts
20 April 2026
16%+14 pts
7 July 2025
1.4%+1.4 pts
12 June 2024
0%
Context
Dubai Harbour has 11 projects under construction, 35% built on average. Dubai Harbour Residences (Area 1) is behind that average.
Harbour One Investment has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Dubai Harbour Residences (Area 1)?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Dubai Harbour Residences (Area 1) be completed?
- The completion date registered with the Dubai Land Department is January 2028. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Dubai Harbour Residences (Area 1) is built?
- 30%, measured at the Land Department site inspection on 11 August 2026. The Land Department engineers have inspected the site 4 times since June 2024.
- Is Dubai Harbour Residences (Area 1) delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of January 2028.
- Who is building Dubai Harbour Residences (Area 1)?
- The registered developer is Harbour One Investment. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Dubai Harbour Residences (Area 1)?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Dubai Harbour Residences (Area 3)Also by Harbour One Investment. 35%, Due January 2028.
- Address The BayNearby in Dubai Harbour. 70%, Due December 2026.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 37%, Due April 2028.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- SeapointNearby in Dubai Harbour. 37%, Due March 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.