Dubai Harbour Residences (Area 1) construction progress
The registered completion date for Dubai Harbour Residences (Area 1) in Dubai Harbour is January 2028. At the last site inspection, in August 2026, it was 30% built. The developer is Harbour One Investment.
30%
Built, at the site inspection of 11 August 2026
On pace for its date
- Registered completion date
- January 2028
- Finish at recent pace
- February 2028
- Construction started
- February 2025
- First registered
- July 2024
- Developer
- Harbour One Investment
- Community
- Dubai Harbour
- Units
- 217
- Escrow bank
- Emirates NBD
- Name in Arabic
- دبي هاربور رزيدنسز (المنطقة 1)
- Project number
- 3133
- Site inspections
- 4
Schedule
Since April 2026 Dubai Harbour Residences (Area 1) has added about 3.9 points a month. That puts 100% around February 2028, within three months of its registered completion date of January 2028.
Site inspections
11 August 2026
30%+14 pts
20 April 2026
16%+14 pts
7 July 2025
1.4%+1.4 pts
12 June 2024
0%
Context
Dubai Harbour has 11 projects under construction, 36% built on average.
Harbour One Investment has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Dubai Harbour Residences (Area 1)?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Dubai Harbour Residences (Area 1) handover date?
- The registered completion date is January 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Dubai Harbour Residences (Area 1)?
- Dubai Harbour Residences (Area 1) was 30% built at the site inspection on 11 August 2026. The site has been inspected 4 times since June 2024. The Land Department took 21 site photos at its inspections.
- Is Dubai Harbour Residences (Area 1) delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of January 2028.
- Who is building Dubai Harbour Residences (Area 1)?
- The registered developer is Harbour One Investment. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Dubai Harbour Residences (Area 1)?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Dubai Harbour Residences (Area 3)Also by Harbour One Investment. 35%, Due January 2028.
- Address The BayNearby in Dubai Harbour. 70%, Due December 2026.
- Sobha Seahaven Tower ANearby in Dubai Harbour. 45%, Due April 2028.
- Damac BayNearby in Dubai Harbour. 34%, Due January 2027.
- SeapointNearby in Dubai Harbour. 37%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.