W Residences At Dubai Harbour construction progress

The registered completion date for W Residences At Dubai Harbour in Dubai Harbour is December 2028. At the last site inspection, in October 2026, it was 4.0% built. The developer is Arada Developments S.o.c.

4.0%

Built, at the site inspection of 13 October 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
September 2042
Construction started
June 2025
First registered
October 2024
Community
Dubai Harbour
Units
494
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
رزيدنسز في دبي هاربر W
Project number
3317
Site inspections
5

Schedule

Between February 2026 and October 2026 the site added about 0.5 points a month. At that rate it would finish around September 2042, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 October 2026

4.0%+2.0 pts

  • W Residences At Dubai Harbour construction site, inspection photo 1, 13 October 2026
  • W Residences At Dubai Harbour construction site, inspection photo 2, 13 October 2026
  • W Residences At Dubai Harbour construction site, inspection photo 3, 13 October 2026
  • W Residences At Dubai Harbour construction site, inspection photo 4, 13 October 2026

6 July 2026

2.0%+2.0 pts

  • W Residences At Dubai Harbour construction site, inspection photo 1, 6 July 2026
  • W Residences At Dubai Harbour construction site, inspection photo 2, 6 July 2026
  • W Residences At Dubai Harbour construction site, inspection photo 3, 6 July 2026
  • W Residences At Dubai Harbour construction site, inspection photo 4, 6 July 2026

16 February 2026

0%+0.0 pts

  • W Residences At Dubai Harbour construction site, inspection photo 1, 16 February 2026
  • W Residences At Dubai Harbour construction site, inspection photo 2, 16 February 2026

26 August 2025

0%

  • W Residences At Dubai Harbour construction site, inspection photo 1, 26 August 2025
  • W Residences At Dubai Harbour construction site, inspection photo 2, 26 August 2025

26 September 2024

0%

  • W Residences At Dubai Harbour construction site, inspection photo 1, 26 September 2024
  • W Residences At Dubai Harbour construction site, inspection photo 2, 26 September 2024
  • W Residences At Dubai Harbour construction site, inspection photo 3, 26 September 2024

All 18 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 36% built on average.

Arada Developments S.o.c has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in W Residences At Dubai Harbour?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the W Residences At Dubai Harbour handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2042. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on W Residences At Dubai Harbour?
W Residences At Dubai Harbour was 4.0% built at the site inspection on 13 October 2026. The site has been inspected 5 times since September 2024. The Land Department took 18 site photos at its inspections.
Is W Residences At Dubai Harbour delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building W Residences At Dubai Harbour?
The registered developer is Arada Developments S.o.c. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for W Residences At Dubai Harbour?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.