Skip to content

W Residences At Dubai Harbour construction progress

W Residences At Dubai Harbour in Dubai Harbour is 2.0% built at the Land Department inspection of July 2026. Developer Arada Developments S.o.c. Completion registered for December 2028.

2.0%

Built, at the Land Department site inspection of 6 July 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
October 2067
Construction started
June 2025
Registered with the Land Department
October 2024
Community
Dubai Harbour
Units
494
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
رزيدنسز في دبي هاربر W
Land Department project number
3317
Land Department site inspections
4

Schedule

Between August 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around October 2067, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

2.0%+2.0 pts

  • W Residences At Dubai Harbour construction site, Land Department inspection photo 1, 6 July 2026
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 2, 6 July 2026
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 3, 6 July 2026
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 4, 6 July 2026

16 February 2026

0%+0.0 pts

  • W Residences At Dubai Harbour construction site, Land Department inspection photo 1, 16 February 2026
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 2, 16 February 2026

26 August 2025

0%

  • W Residences At Dubai Harbour construction site, Land Department inspection photo 1, 26 August 2025
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 2, 26 August 2025

26 September 2024

0%

  • W Residences At Dubai Harbour construction site, Land Department inspection photo 1, 26 September 2024
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 2, 26 September 2024
  • W Residences At Dubai Harbour construction site, Land Department inspection photo 3, 26 September 2024

All 12 site photos, by inspection date

Context

Dubai Harbour has 11 projects under construction, 35% built on average.

Arada Developments S.o.c has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in W Residences At Dubai Harbour?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will W Residences At Dubai Harbour be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around October 2067. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of W Residences At Dubai Harbour is built?
2.0%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 4 times since September 2024.
Is W Residences At Dubai Harbour delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building W Residences At Dubai Harbour?
The registered developer is Arada Developments S.o.c. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for W Residences At Dubai Harbour?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.