Nobles construction progress

The register lists Nobles in Business Bay as complete, with a registered completion date of August 2024. Its last site inspection on record was in October 2024. The developer is Tiger Properties.

100%

Built, at the site inspection of 24 October 2024

Construction complete

Registered completion date
August 2024
Construction started
February 2020
First registered
February 2021
Community
Business Bay
Units
562
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
نوبلز
Project number
2208
Site inspections
8

Schedule

The register lists Nobles as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2021202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 October 2024

100%+9.0 pts

  • Nobles construction site, inspection photo 1, 24 October 2024
  • Nobles construction site, inspection photo 2, 24 October 2024
  • Nobles construction site, inspection photo 3, 24 October 2024
  • Nobles construction site, inspection photo 4, 24 October 2024

12 July 2024

91%+35 pts

  • Nobles construction site, inspection photo 1, 12 July 2024
  • Nobles construction site, inspection photo 2, 12 July 2024
  • Nobles construction site, inspection photo 3, 12 July 2024
  • Nobles construction site, inspection photo 4, 12 July 2024

20 October 2023

56%+22 pts

  • Nobles construction site, inspection photo 1, 20 October 2023
  • Nobles construction site, inspection photo 2, 20 October 2023
  • Nobles construction site, inspection photo 3, 20 October 2023
  • Nobles construction site, inspection photo 4, 20 October 2023

7 April 2023

34%+6.3 pts

  • Nobles construction site, inspection photo 1, 7 April 2023
  • Nobles construction site, inspection photo 2, 7 April 2023
  • Nobles construction site, inspection photo 3, 7 April 2023
  • Nobles construction site, inspection photo 4, 7 April 2023

26 December 2022

27%+11 pts

  • Nobles construction site, inspection photo 1, 26 December 2022
  • Nobles construction site, inspection photo 2, 26 December 2022
  • Nobles construction site, inspection photo 3, 26 December 2022
  • Nobles construction site, inspection photo 4, 26 December 2022

21 July 2022

17%+7.3 pts

  • Nobles construction site, inspection photo 1, 21 July 2022
  • Nobles construction site, inspection photo 2, 21 July 2022
  • Nobles construction site, inspection photo 3, 21 July 2022
  • Nobles construction site, inspection photo 4, 21 July 2022

3 March 2022

9.4%+5.9 pts

  • Nobles construction site, inspection photo 1, 3 March 2022
  • Nobles construction site, inspection photo 2, 3 March 2022
  • Nobles construction site, inspection photo 3, 3 March 2022
  • Nobles construction site, inspection photo 4, 3 March 2022

19 November 2020

3.5%

  • Nobles construction site, inspection photo 1, 19 November 2020
  • Nobles construction site, inspection photo 2, 19 November 2020
  • Nobles construction site, inspection photo 3, 19 November 2020
  • Nobles construction site, inspection photo 4, 19 November 2020

All 70 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nobles?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Nobles handover date?
Construction of Nobles is recorded as complete, with a registered completion date of August 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Nobles?
Nobles was 100% built at the site inspection on 24 October 2024. The site has been inspected 8 times since November 2020. The Land Department took 70 site photos at its inspections.
Is Nobles delayed?
The register lists construction as complete.
Who is building Nobles?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Nobles?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.