Volga Tower construction progress
Volga Tower in Jumeirah Village Triangle is 51% built at the Land Department inspection of October 2026. Developer Tiger Properties.
51%
Built, at the Land Department site inspection of 5 October 2026
- Finish at recent pace
- April 2028
- Construction started
- September 2023
- Registered with the Land Department
- September 2023
- Developer
- Tiger Properties
- Community
- Jumeirah Village Triangle
- Units
- 391
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- فولجا تاور
- Land Department project number
- 2715
- Land Department site inspections
- 7
Schedule
Since December 2025 Volga Tower has added about 2.7 points a month. At that rate the site reaches 100% around April 2028. The Land Department has no completion date on record to compare it with.
Site inspections
5 October 2026
51%+13 pts
25 June 2026
38%+3.9 pts
6 April 2026
34%+8.0 pts
29 December 2025
26%+7.8 pts
24 July 2025
18%+6.6 pts
20 February 2025
12%+12 pts
12 July 2023
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average.
Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Volga Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Volga Tower be completed?
- The Land Department has no completion date on record for Volga Tower yet.
- How much of Volga Tower is built?
- 51%, measured at the Land Department site inspection on 5 October 2026. The Land Department engineers have inspected the site 7 times since July 2023.
- Who is building Volga Tower?
- The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Volga Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tiger Sky TowerAlso by Tiger Properties. 10%.
- Altai TowerAlso by Tiger Properties. 98%, Due January 2026, passed.
- Red SquareAlso by Tiger Properties. 27%.
- Jade TowerAlso by Tiger Properties. 11%.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Santorini Residences By LoutrakiNearby in Jumeirah Village Triangle. 43%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.














.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)