Jade Tower construction progress

The registered completion date for Jade Tower in Majan is March 2027. At the last site inspection, in October 2026, it was 11% built. The developer is Tiger Properties.

11%

Built, at the site inspection of 2 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
April 2038
Construction started
April 2024
First registered
June 2024
Community
Majan
Units
436
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج جايد
Project number
3074
Site inspections
6

Schedule

Between December 2025 and October 2026 the site added about 0.6 points a month. At that rate it would finish around April 2038, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 October 2026

11%+1.6 pts

  • Jade Tower construction site, inspection photo 1, 2 October 2026
  • Jade Tower construction site, inspection photo 2, 2 October 2026
  • Jade Tower construction site, inspection photo 3, 2 October 2026
  • Jade Tower construction site, inspection photo 4, 2 October 2026

18 June 2026

9.4%+1.8 pts

  • Jade Tower construction site, inspection photo 1, 18 June 2026
  • Jade Tower construction site, inspection photo 2, 18 June 2026
  • Jade Tower construction site, inspection photo 3, 18 June 2026
  • Jade Tower construction site, inspection photo 4, 18 June 2026

1 April 2026

7.6%+2.4 pts

  • Jade Tower construction site, inspection photo 1, 1 April 2026
  • Jade Tower construction site, inspection photo 2, 1 April 2026
  • Jade Tower construction site, inspection photo 3, 1 April 2026

30 December 2025

5.2%+5.1 pts

  • Jade Tower construction site, inspection photo 1, 30 December 2025
  • Jade Tower construction site, inspection photo 2, 30 December 2025
  • Jade Tower construction site, inspection photo 3, 30 December 2025
  • Jade Tower construction site, inspection photo 4, 30 December 2025

25 February 2025

0.1%+0.1 pts

  • Jade Tower construction site, inspection photo 1, 25 February 2025
  • Jade Tower construction site, inspection photo 2, 25 February 2025
  • Jade Tower construction site, inspection photo 3, 25 February 2025

9 May 2024

0%

  • Jade Tower construction site, inspection photo 1, 9 May 2024
  • Jade Tower construction site, inspection photo 2, 9 May 2024

All 25 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Jade Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Jade Tower handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Jade Tower?
Jade Tower was 11% built at the site inspection on 2 October 2026. The site has been inspected 6 times since May 2024. The Land Department took 25 site photos at its inspections.
Is Jade Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Jade Tower?
The registered developer is Tiger Properties. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Jade Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.