Jade Tower construction progress
The registered completion date for Jade Tower in Majan is March 2027. At the last site inspection, in October 2026, it was 11% built. The developer is Tiger Properties.
11%
Built, at the site inspection of 2 October 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- April 2038
- Construction started
- April 2024
- First registered
- June 2024
- Developer
- Tiger Properties
- Community
- Majan
- Units
- 436
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- برج جايد
- Project number
- 3074
- Site inspections
- 6
Schedule
Between December 2025 and October 2026 the site added about 0.6 points a month. At that rate it would finish around April 2038, more than three months after its registered date of March 2027.
Site inspections
2 October 2026
11%+1.6 pts
18 June 2026
9.4%+1.8 pts
1 April 2026
7.6%+2.4 pts
30 December 2025
5.2%+5.1 pts
25 February 2025
0.1%+0.1 pts
9 May 2024
0%
Context
Majan has 25 projects under construction, 28% built on average.
Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Jade Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Jade Tower handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Jade Tower?
- Jade Tower was 11% built at the site inspection on 2 October 2026. The site has been inspected 6 times since May 2024. The Land Department took 25 site photos at its inspections.
- Is Jade Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Jade Tower?
- The registered developer is Tiger Properties. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Jade Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tiger Sky TowerAlso by Tiger Properties. 10%.
- Volga TowerAlso by Tiger Properties. 51%.
- Red SquareAlso by Tiger Properties. 27%.
- Guzel TowersAlso by Tiger Properties. 7.3%, Due December 2027.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)