Red Square construction progress

No completion date is registered for Red Square in Jumeirah Village Triangle yet. At the last site inspection, in March 2026, it was 27% built. The developer is Tiger Properties.

27%

Built, at the site inspection of 27 March 2026

Finish at recent pace
March 2029
Construction started
January 2024
First registered
February 2024
Units
835
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ريد سكوير
Project number
2789
Site inspections
4

Schedule

Since July 2025 Red Square has added about 2.0 points a month. At that rate the site reaches 100% around March 2029. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

27 March 2026

27%+18 pts

  • Red Square construction site, inspection photo 1, 27 March 2026
  • Red Square construction site, inspection photo 2, 27 March 2026
  • Red Square construction site, inspection photo 3, 27 March 2026
  • Red Square construction site, inspection photo 4, 27 March 2026

3 July 2025

8.8%+1.6 pts

  • Red Square construction site, inspection photo 1, 3 July 2025
  • Red Square construction site, inspection photo 2, 3 July 2025
  • Red Square construction site, inspection photo 3, 3 July 2025
  • Red Square construction site, inspection photo 4, 3 July 2025

12 February 2025

7.2%+7.2 pts

  • Red Square construction site, inspection photo 1, 12 February 2025
  • Red Square construction site, inspection photo 2, 12 February 2025
  • Red Square construction site, inspection photo 3, 12 February 2025

19 January 2024

0%

  • Red Square construction site, inspection photo 1, 19 January 2024
  • Red Square construction site, inspection photo 2, 19 January 2024
  • Red Square construction site, inspection photo 3, 19 January 2024

All 18 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Red Square?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Red Square handover date?
No completion date is on record for Red Square yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Red Square?
Red Square was 27% built at the site inspection on 27 March 2026. The site has been inspected 4 times since January 2024. The Land Department took 18 site photos at its inspections.
Who is building Red Square?
The registered developer is Tiger Properties. It has 7 other projects under construction in Dubai.
Which bank holds the escrow account for Red Square?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.