Tiger Properties projects under construction
Tiger Properties has 8 projects under construction in Dubai. On average they are 15% built. The next one due is Jade Tower, in March 2027.
- Volga TowerJumeirah Village Triangle51%No date set
- Red SquareJumeirah Village Triangle27%No date set
- Jade TowerMajan11%Due March 2027
- Tiger Sky TowerBusiness Bay10%No date set
- Guzel TowersJumeirah Village Triangle7.3%Due December 2027
- Sky Gate TowerJumeirah Village Triangle4.7%Due February 2028
- Auresta TowerJumeirah Village Circle4.4%Due December 2028
- Ananda ResidencesMotor City3.2%Due May 2028
Questions
How many projects is Tiger Properties building in Dubai?
8 projects are under construction, 15% built on average at the latest site inspections.
Which Tiger Properties projects finish next?
By registered completion date: Jade Tower (March 2027, 11% built), Guzel Towers (December 2027, 7.3% built) and Sky Gate Tower (February 2028, 4.7% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Tiger Properties projects delayed?
No. Every one of its projects with a registered completion date is still inside it.
Where is Tiger Properties building?
Its projects are in Jumeirah Village Triangle (4), Business Bay (1) and Jumeirah Village Circle (1), and 2 other communities.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.