15 Northside construction progress

The register lists 15 Northside in Business Bay as complete, with a registered completion date of April 2023. Its last site inspection on record was in April 2023. The developer is Select Global Development.

100%

Built, at the site inspection of 25 April 2023

Construction complete

Registered completion date
April 2023
Construction started
December 2020
First registered
December 2020
Community
Business Bay
Units
358
Escrow bank
Emirates NBD
Name in Arabic
15 نورث سايد
Project number
2214
Site inspections
6

Schedule

The register lists 15 Northside as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 April 2023

100%+11 pts

  • 15 Northside construction site, inspection photo 1, 25 April 2023
  • 15 Northside construction site, inspection photo 2, 25 April 2023
  • 15 Northside construction site, inspection photo 3, 25 April 2023
  • 15 Northside construction site, inspection photo 4, 25 April 2023

13 December 2022

89%+8.3 pts

  • 15 Northside construction site, inspection photo 1, 13 December 2022
  • 15 Northside construction site, inspection photo 2, 13 December 2022
  • 15 Northside construction site, inspection photo 3, 13 December 2022
  • 15 Northside construction site, inspection photo 4, 13 December 2022

17 August 2022

80%+16 pts

  • 15 Northside construction site, inspection photo 1, 17 August 2022
  • 15 Northside construction site, inspection photo 2, 17 August 2022
  • 15 Northside construction site, inspection photo 3, 17 August 2022
  • 15 Northside construction site, inspection photo 4, 17 August 2022

19 January 2022

64%+23 pts

  • 15 Northside construction site, inspection photo 1, 19 January 2022
  • 15 Northside construction site, inspection photo 2, 19 January 2022
  • 15 Northside construction site, inspection photo 3, 19 January 2022
  • 15 Northside construction site, inspection photo 4, 19 January 2022

10 August 2021

41%+0.0 pts

  • 15 Northside construction site, inspection photo 1, 10 August 2021
  • 15 Northside construction site, inspection photo 2, 10 August 2021
  • 15 Northside construction site, inspection photo 3, 10 August 2021
  • 15 Northside construction site, inspection photo 4, 10 August 2021

24 June 2020

41%

  • 15 Northside construction site, inspection photo 1, 24 June 2020
  • 15 Northside construction site, inspection photo 2, 24 June 2020
  • 15 Northside construction site, inspection photo 3, 24 June 2020
  • 15 Northside construction site, inspection photo 4, 24 June 2020

All 70 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Select Global Development has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 15 Northside?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the 15 Northside handover date?
Construction of 15 Northside is recorded as complete, with a registered completion date of April 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on 15 Northside?
15 Northside was 100% built at the site inspection on 25 April 2023. The site has been inspected 6 times since June 2020. The Land Department took 70 site photos at its inspections.
Is 15 Northside delayed?
The register lists construction as complete.
Who is building 15 Northside?
The registered developer is Select Global Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for 15 Northside?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.