15 Northside construction photos

70 photos from 6 site inspections, newest first. The percentage is how much of 15 Northside was built on the day of each visit.

25 April 2023100% built

13 December 202289% built

17 August 202280% built

19 January 202264% built

10 August 202141% built

24 June 202041% built

Back to 15 Northside construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.