Prime Residency 3 construction progress
The register lists Prime Residency 3 in Al Furjan as complete, with a registered completion date of December 2024. Its last site inspection on record was in December 2024. The developer is Prescott Real Estate Development.
100%
Built, at the site inspection of 6 December 2024
Construction complete
- Registered completion date
- December 2024
- Construction started
- June 2021
- First registered
- October 2021
- Developer
- Prescott Real Estate Development
- Community
- Al Furjan
- Units
- 292
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بريم ريزيدنسي 3
- Project number
- 2276
- Site inspections
- 12
Schedule
The register lists Prime Residency 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
6 December 2024
100%+9.2 pts
30 April 2024
91%+15 pts
18 December 2023
75%+12 pts
5 October 2023
63%+11 pts
17 July 2023
52%+12 pts
13 March 2023
40%+12 pts
31 October 2022
28%+7.9 pts
18 May 2022
20%+1.7 pts
5 April 2022
18%+2.3 pts
27 January 2022
16%+1.0 pts
Context
Al Furjan has 38 projects under construction, 32% built on average.
Prescott Real Estate Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Prime Residency 3?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Prime Residency 3 handover date?
- Construction of Prime Residency 3 is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Prime Residency 3?
- Prime Residency 3 was 100% built at the site inspection on 6 December 2024. The site has been inspected 12 times since August 2021. The Land Department took 108 site photos at its inspections.
- Is Prime Residency 3 delayed?
- The register lists construction as complete.
- Who is building Prime Residency 3?
- The registered developer is Prescott Real Estate Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Prime Residency 3?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Serene Gardens By PrescottAlso by Prescott Real Estate Development. 62%.
- Serene Gardens 2 By PrescottAlso by Prescott Real Estate Development. 70%.
- Fairway Residences By PrescottAlso by Prescott Real Estate Development. 50%.
- Legado By PrescottAlso by Prescott Real Estate Development. 23%, Due August 2027.
- Trussardi ResidencesNearby in Al Furjan. 36%, Due January 2026, passed.
- Rosalia ResidencesNearby in Al Furjan. 93%.
- The Stella ResidencesNearby in Al Furjan. 71%, Due December 2025, passed.
- Symbolic AuraNearby in Al Furjan. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)