Prime Residency 3 construction photos
108 photos from 12 site inspections, newest first. The percentage is how much of Prime Residency 3 was built on the day of each visit.
6 December 2024100% built
30 April 202491% built
18 December 202375% built
5 October 202363% built
17 July 202352% built
13 March 202340% built
31 October 202228% built
18 May 202220% built
5 April 202218% built
27 January 202216% built
19 September 202115% built
10 August 202110% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.