Azizi. Liatris construction progress

The register lists Azizi. Liatris in Al Furjan as complete, with a registered completion date of October 2016. Its last site inspection on record was in November 2016. The developer is Azizi Developments.

100%

Built, at the site inspection of 9 November 2016

Construction complete

Registered completion date
October 2016
Construction started
June 2014
First registered
May 2014
Community
Al Furjan
Units
129
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي لياتريس
Project number
1511
Site inspections
5

Schedule

The register lists Azizi. Liatris as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2016

100%+15 pts

  • Azizi. Liatris construction site, inspection photo 1, 9 November 2016
  • Azizi. Liatris construction site, inspection photo 2, 9 November 2016
  • Azizi. Liatris construction site, inspection photo 3, 9 November 2016
  • Azizi. Liatris construction site, inspection photo 4, 9 November 2016

9 June 2016

85%+26 pts

  • Azizi. Liatris construction site, inspection photo 1, 9 June 2016
  • Azizi. Liatris construction site, inspection photo 2, 9 June 2016
  • Azizi. Liatris construction site, inspection photo 3, 9 June 2016
  • Azizi. Liatris construction site, inspection photo 4, 9 June 2016

25 January 2016

59%+19 pts

  • Azizi. Liatris construction site, inspection photo 1, 25 January 2016
  • Azizi. Liatris construction site, inspection photo 2, 25 January 2016
  • Azizi. Liatris construction site, inspection photo 3, 25 January 2016
  • Azizi. Liatris construction site, inspection photo 4, 25 January 2016

29 September 2015

40%+23 pts

  • Azizi. Liatris construction site, inspection photo 1, 29 September 2015
  • Azizi. Liatris construction site, inspection photo 2, 29 September 2015
  • Azizi. Liatris construction site, inspection photo 3, 29 September 2015
  • Azizi. Liatris construction site, inspection photo 4, 29 September 2015

10 March 2015

17%

  • Azizi. Liatris construction site, inspection photo 1, 10 March 2015
  • Azizi. Liatris construction site, inspection photo 2, 10 March 2015
  • Azizi. Liatris construction site, inspection photo 3, 10 March 2015
  • Azizi. Liatris construction site, inspection photo 4, 10 March 2015

All 47 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi. Liatris?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi. Liatris handover date?
Construction of Azizi. Liatris is recorded as complete, with a registered completion date of October 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi. Liatris?
Azizi. Liatris was 100% built at the site inspection on 9 November 2016. The site has been inspected 5 times since March 2015. The Land Department took 47 site photos at its inspections.
Is Azizi. Liatris delayed?
The register lists construction as complete.
Who is building Azizi. Liatris?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi. Liatris?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.