Azizi Farishta Residence construction progress

The register lists Azizi Farishta Residence in Al Furjan as complete, with a registered completion date of March 2020. Its last site inspection on record was in March 2020. The developer is Azizi Developments.

100%

Built, at the site inspection of 16 March 2020

Construction complete

Registered completion date
March 2020
Construction started
September 2016
First registered
October 2016
Community
Al Furjan
Units
295
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي فاريشتا ريزيدنس
Project number
1810
Site inspections
8

Schedule

The register lists Azizi Farishta Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 March 2020

100%+12 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 16 March 2020
  • Azizi Farishta Residence construction site, inspection photo 2, 16 March 2020
  • Azizi Farishta Residence construction site, inspection photo 3, 16 March 2020
  • Azizi Farishta Residence construction site, inspection photo 4, 16 March 2020

12 September 2019

88%+6.2 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 12 September 2019
  • Azizi Farishta Residence construction site, inspection photo 2, 12 September 2019
  • Azizi Farishta Residence construction site, inspection photo 3, 12 September 2019
  • Azizi Farishta Residence construction site, inspection photo 4, 12 September 2019

14 July 2019

82%+6.0 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 14 July 2019
  • Azizi Farishta Residence construction site, inspection photo 2, 14 July 2019
  • Azizi Farishta Residence construction site, inspection photo 3, 14 July 2019
  • Azizi Farishta Residence construction site, inspection photo 4, 14 July 2019

22 January 2019

76%+9.1 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 22 January 2019
  • Azizi Farishta Residence construction site, inspection photo 2, 22 January 2019
  • Azizi Farishta Residence construction site, inspection photo 3, 22 January 2019
  • Azizi Farishta Residence construction site, inspection photo 4, 22 January 2019

12 August 2018

67%+24 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 12 August 2018
  • Azizi Farishta Residence construction site, inspection photo 2, 12 August 2018
  • Azizi Farishta Residence construction site, inspection photo 3, 12 August 2018
  • Azizi Farishta Residence construction site, inspection photo 4, 12 August 2018

18 January 2018

43%+19 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 18 January 2018
  • Azizi Farishta Residence construction site, inspection photo 2, 18 January 2018
  • Azizi Farishta Residence construction site, inspection photo 3, 18 January 2018
  • Azizi Farishta Residence construction site, inspection photo 4, 18 January 2018

23 August 2017

24%+9.4 pts

  • Azizi Farishta Residence construction site, inspection photo 1, 23 August 2017
  • Azizi Farishta Residence construction site, inspection photo 2, 23 August 2017
  • Azizi Farishta Residence construction site, inspection photo 3, 23 August 2017

25 April 2017

14%

  • Azizi Farishta Residence construction site, inspection photo 1, 25 April 2017
  • Azizi Farishta Residence construction site, inspection photo 2, 25 April 2017
  • Azizi Farishta Residence construction site, inspection photo 3, 25 April 2017
  • Azizi Farishta Residence construction site, inspection photo 4, 25 April 2017

All 68 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Farishta Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Farishta Residence handover date?
Construction of Azizi Farishta Residence is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Farishta Residence?
Azizi Farishta Residence was 100% built at the site inspection on 16 March 2020. The site has been inspected 8 times since April 2017. The Land Department took 68 site photos at its inspections.
Is Azizi Farishta Residence delayed?
The register lists construction as complete.
Who is building Azizi Farishta Residence?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Farishta Residence?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.