Reef 998 construction progress
The registered completion date for Reef 998 in Dubai Land Residence Complex is June 2028. At the last site inspection, in August 2026, it was 2.1% built. The developer is Reef Luxury Development.
2.1%
Built, at the site inspection of 27 August 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- November 2050
- Construction started
- June 2025
- First registered
- May 2025
- Developer
- Reef Luxury Development
- Community
- Dubai Land Residence Complex
- Units
- 339
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ريف 998
- Project number
- 3651
- Site inspections
- 4
Schedule
Between March 2026 and August 2026 the site added about 0.3 points a month. At that rate it would finish around November 2050, more than three months after its registered date of June 2028.
Site inspections
27 August 2026
2.1%+1.2 pts
18 June 2026
0.8%+0.6 pts
10 March 2026
0.2%+0.2 pts
3 April 2025
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Reef 998?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Reef 998 handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2050. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Reef 998?
- Reef 998 was 2.1% built at the site inspection on 27 August 2026. The site has been inspected 4 times since April 2025. The Land Department took 14 site photos at its inspections.
- Is Reef 998 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Reef 998?
- The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Reef 998?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Reef 1000Also by Reef Luxury Development. 67%, Due December 2026.
- 999 Residences By Reef Luxury DevelopmentAlso by Reef Luxury Development. 13%, Due June 2027.
- 997 Residences By Reef Luxury DevelopmentAlso by Reef Luxury Development. 4.9%, Due March 2028.
- Reef 996Also by Reef Luxury Development. 0.1%, Due September 2028.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.