Reef 1000 construction progress
The registered completion date for Reef 1000 in Dubai Land Residence Complex is December 2026. At the last site inspection, in October 2026, it was 67% built. The developer is Reef Luxury Development.
67%
Built, at the site inspection of 5 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- June 2027
- Construction started
- November 2024
- First registered
- October 2024
- Developer
- Reef Luxury Development
- Community
- Dubai Land Residence Complex
- Units
- 126
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ريف 1000
- Project number
- 3219
- Site inspections
- 7
Schedule
Between October 2025 and October 2026 the site added about 4.1 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.
Site inspections
5 October 2026
67%+17 pts
14 July 2026
50%+19 pts
24 April 2026
31%+7.7 pts
9 February 2026
23%+5.3 pts
7 October 2025
18%+7.6 pts
9 July 2025
10%+10 pts
8 August 2024
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Reef 1000?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Reef 1000 handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Reef 1000?
- Reef 1000 was 67% built at the site inspection on 5 October 2026. The site has been inspected 7 times since August 2024. The Land Department took 60 site photos at its inspections.
- Is Reef 1000 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Reef 1000?
- The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Reef 1000?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 999 Residences By Reef Luxury DevelopmentAlso by Reef Luxury Development. 13%, Due June 2027.
- Reef 998Also by Reef Luxury Development. 2.1%, Due June 2028.
- 997 Residences By Reef Luxury DevelopmentAlso by Reef Luxury Development. 4.9%, Due March 2028.
- Reef 996Also by Reef Luxury Development. 0.1%, Due September 2028.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)