Reef 1000 construction progress

Reef 1000 in Dubai Land Residence Complex is 67% built at the Land Department inspection of October 2026. Developer Reef Luxury Development. Completion registered for December 2026.

67%

Built, at the Land Department site inspection of 5 October 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
June 2027
Construction started
November 2024
Registered with the Land Department
October 2024
Units
126
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ريف 1000
Land Department project number
3219
Land Department site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 4.1 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 October 2026

67%+17 pts

  • Reef 1000 construction site, Land Department inspection photo 1, 5 October 2026
  • Reef 1000 construction site, Land Department inspection photo 2, 5 October 2026
  • Reef 1000 construction site, Land Department inspection photo 3, 5 October 2026
  • Reef 1000 construction site, Land Department inspection photo 4, 5 October 2026

14 July 2026

50%+19 pts

  • Reef 1000 construction site, Land Department inspection photo 1, 14 July 2026
  • Reef 1000 construction site, Land Department inspection photo 2, 14 July 2026
  • Reef 1000 construction site, Land Department inspection photo 3, 14 July 2026
  • Reef 1000 construction site, Land Department inspection photo 4, 14 July 2026

24 April 2026

31%+7.7 pts

  • Reef 1000 construction site, Land Department inspection photo 1, 24 April 2026
  • Reef 1000 construction site, Land Department inspection photo 2, 24 April 2026
  • Reef 1000 construction site, Land Department inspection photo 3, 24 April 2026
  • Reef 1000 construction site, Land Department inspection photo 4, 24 April 2026

9 February 2026

23%+5.3 pts

  • Reef 1000 construction site, Land Department inspection photo 1, 9 February 2026
  • Reef 1000 construction site, Land Department inspection photo 2, 9 February 2026
  • Reef 1000 construction site, Land Department inspection photo 3, 9 February 2026
  • Reef 1000 construction site, Land Department inspection photo 4, 9 February 2026

7 October 2025

18%+7.6 pts

  • Reef 1000 construction site, Land Department inspection photo 1, 7 October 2025
  • Reef 1000 construction site, Land Department inspection photo 2, 7 October 2025
  • Reef 1000 construction site, Land Department inspection photo 3, 7 October 2025
  • Reef 1000 construction site, Land Department inspection photo 4, 7 October 2025

9 July 2025

10%+10 pts

  • Reef 1000 construction site, Land Department inspection photo 1, 9 July 2025
  • Reef 1000 construction site, Land Department inspection photo 2, 9 July 2025
  • Reef 1000 construction site, Land Department inspection photo 3, 9 July 2025
  • Reef 1000 construction site, Land Department inspection photo 4, 9 July 2025

8 August 2024

0%

  • Reef 1000 construction site, Land Department inspection photo 1, 8 August 2024
  • Reef 1000 construction site, Land Department inspection photo 2, 8 August 2024
  • Reef 1000 construction site, Land Department inspection photo 3, 8 August 2024

All 60 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Reef 1000?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Reef 1000 be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Reef 1000 is built?
67%, measured at the Land Department site inspection on 5 October 2026. The Land Department engineers have inspected the site 7 times since August 2024.
Is Reef 1000 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Reef 1000?
The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Reef 1000?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.