997 Residences By Reef Luxury Development construction progress

997 Residences By Reef Luxury Development in Palm Deira is 4.9% built at the Land Department inspection of August 2026. Developer Reef Luxury Development. Completion registered for March 2028.

4.9%

Built, at the Land Department site inspection of 27 August 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
October 2035
Construction started
July 2025
Registered with the Land Department
September 2025
Community
Palm Deira
Units
63
Escrow bank
First Abu Dhabi Bank
Name in Arabic
997ريزيدنسز من ريف للتطوير الفاخر
Land Department project number
3837
Land Department site inspections
4

Schedule

Between March 2026 and August 2026 the site added about 0.9 points a month. At that rate it would finish around October 2035, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 August 2026

4.9%+0.9 pts

  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 1, 27 August 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 2, 27 August 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 3, 27 August 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 4, 27 August 2026

24 June 2026

4.0%+4.0 pts

  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 1, 24 June 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 2, 24 June 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 3, 24 June 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 4, 24 June 2026

10 March 2026

0%+0.0 pts

  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 1, 10 March 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 2, 10 March 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 3, 10 March 2026
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 4, 10 March 2026

17 June 2025

0%

  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 1, 17 June 2025
  • 997 Residences By Reef Luxury Development construction site, Land Department inspection photo 2, 17 June 2025

All 15 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 997 Residences By Reef Luxury Development?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will 997 Residences By Reef Luxury Development be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around October 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 997 Residences By Reef Luxury Development is built?
4.9%, measured at the Land Department site inspection on 27 August 2026. The Land Department engineers have inspected the site 4 times since June 2025.
Is 997 Residences By Reef Luxury Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building 997 Residences By Reef Luxury Development?
The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for 997 Residences By Reef Luxury Development?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.