Skip to content

997 Residences By Reef Luxury Development construction progress

The registered completion date for 997 Residences By Reef Luxury Development in Palm Deira is March 2028. At the last site inspection, in August 2026, it was 4.9% built. The developer is Reef Luxury Development.

4.9%

Built, at the site inspection of 27 August 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
October 2035
Construction started
July 2025
First registered
September 2025
Community
Palm Deira
Units
63
Escrow bank
First Abu Dhabi Bank
Name in Arabic
997ريزيدنسز من ريف للتطوير الفاخر
Project number
3837
Site inspections
4

Schedule

Between March 2026 and August 2026 the site added about 0.9 points a month. At that rate it would finish around October 2035, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 August 2026

4.9%+0.9 pts

  • 997 Residences By Reef Luxury Development construction site, inspection photo 1, 27 August 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 2, 27 August 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 3, 27 August 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 4, 27 August 2026

24 June 2026

4.0%+4.0 pts

  • 997 Residences By Reef Luxury Development construction site, inspection photo 1, 24 June 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 2, 24 June 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 3, 24 June 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 4, 24 June 2026

10 March 2026

0%+0.0 pts

  • 997 Residences By Reef Luxury Development construction site, inspection photo 1, 10 March 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 2, 10 March 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 3, 10 March 2026
  • 997 Residences By Reef Luxury Development construction site, inspection photo 4, 10 March 2026

17 June 2025

0%

  • 997 Residences By Reef Luxury Development construction site, inspection photo 1, 17 June 2025
  • 997 Residences By Reef Luxury Development construction site, inspection photo 2, 17 June 2025

All 15 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in 997 Residences By Reef Luxury Development?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the 997 Residences By Reef Luxury Development handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on 997 Residences By Reef Luxury Development?
997 Residences By Reef Luxury Development was 4.9% built at the site inspection on 27 August 2026. The site has been inspected 4 times since June 2025. The Land Department took 15 site photos at its inspections.
Is 997 Residences By Reef Luxury Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building 997 Residences By Reef Luxury Development?
The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for 997 Residences By Reef Luxury Development?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.