Reef 996 construction progress

The registered completion date for Reef 996 in International Media Production Zone is September 2028. At the last site inspection, in September 2026, it was 0.1% built. The developer is Reef Luxury Development.

0.1%

Built, at the site inspection of 1 September 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
August 2502
Construction started
October 2025
First registered
November 2025
Units
505
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ريف 996
Project number
4062
Site inspections
4

Schedule

Between March 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around August 2502, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 September 2026

0.1%+0.1 pts

  • Reef 996 construction site, inspection photo 1, 1 September 2026
  • Reef 996 construction site, inspection photo 2, 1 September 2026
  • Reef 996 construction site, inspection photo 3, 1 September 2026

8 June 2026

0.1%+0.1 pts

  • Reef 996 construction site, inspection photo 1, 8 June 2026
  • Reef 996 construction site, inspection photo 2, 8 June 2026
  • Reef 996 construction site, inspection photo 3, 8 June 2026
  • Reef 996 construction site, inspection photo 4, 8 June 2026

11 March 2026

0%

  • Reef 996 construction site, inspection photo 1, 11 March 2026
  • Reef 996 construction site, inspection photo 2, 11 March 2026
  • Reef 996 construction site, inspection photo 3, 11 March 2026
  • Reef 996 construction site, inspection photo 4, 11 March 2026

27 August 2025

0%

  • Reef 996 construction site, inspection photo 1, 27 August 2025
  • Reef 996 construction site, inspection photo 2, 27 August 2025

All 13 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 23% built on average.

Reef Luxury Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Reef 996?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Reef 996 handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2502. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Reef 996?
Reef 996 was 0.1% built at the site inspection on 1 September 2026. The site has been inspected 4 times since August 2025. The Land Department took 13 site photos at its inspections.
Is Reef 996 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Reef 996?
The registered developer is Reef Luxury Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Reef 996?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.