Reportage Village 1 construction progress

Reportage Village 1 in Wadi Al Safa 7 is 25% built at the Land Department inspection of August 2026. Developer Reportage Prime Properties. Completion registered for December 2027.

25%

Built, at the Land Department site inspection of 20 August 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
October 2030
Construction started
December 2023
Registered with the Land Department
November 2023
Units
1,753
Escrow bank
Al Masraf
Name in Arabic
ريبورتاج فيلدج 1
Land Department project number
2784
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around October 2030, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%2024202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 August 2026

25%+4.3 pts

  • Reportage Village 1 construction site, Land Department inspection photo 1, 20 August 2026
  • Reportage Village 1 construction site, Land Department inspection photo 2, 20 August 2026
  • Reportage Village 1 construction site, Land Department inspection photo 3, 20 August 2026
  • Reportage Village 1 construction site, Land Department inspection photo 4, 20 August 2026

5 May 2026

21%+2.6 pts

  • Reportage Village 1 construction site, Land Department inspection photo 1, 5 May 2026
  • Reportage Village 1 construction site, Land Department inspection photo 2, 5 May 2026
  • Reportage Village 1 construction site, Land Department inspection photo 3, 5 May 2026
  • Reportage Village 1 construction site, Land Department inspection photo 4, 5 May 2026

10 February 2026

18%+7.0 pts

  • Reportage Village 1 construction site, Land Department inspection photo 1, 10 February 2026
  • Reportage Village 1 construction site, Land Department inspection photo 2, 10 February 2026
  • Reportage Village 1 construction site, Land Department inspection photo 3, 10 February 2026
  • Reportage Village 1 construction site, Land Department inspection photo 4, 10 February 2026

11 November 2025

11%+9.1 pts

  • Reportage Village 1 construction site, Land Department inspection photo 1, 11 November 2025
  • Reportage Village 1 construction site, Land Department inspection photo 2, 11 November 2025
  • Reportage Village 1 construction site, Land Department inspection photo 3, 11 November 2025
  • Reportage Village 1 construction site, Land Department inspection photo 4, 11 November 2025

11 April 2025

2.0%

  • Reportage Village 1 construction site, Land Department inspection photo 1, 11 April 2025
  • Reportage Village 1 construction site, Land Department inspection photo 2, 11 April 2025
  • Reportage Village 1 construction site, Land Department inspection photo 3, 11 April 2025
  • Reportage Village 1 construction site, Land Department inspection photo 4, 11 April 2025

All 53 site photos, by inspection date

Context

Wadi Al Safa 7 has 4 projects under construction, 20% built on average.

Reportage Prime Properties has 9 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Reportage Village 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Reportage Village 1 be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Reportage Village 1 is built?
25%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 5 times since April 2025.
Is Reportage Village 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Reportage Village 1?
The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Reportage Village 1?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.