Reportage Village 1 construction progress
Reportage Village 1 in Wadi Al Safa 7 is 25% built at the Land Department inspection of August 2026. Developer Reportage Prime Properties. Completion registered for December 2027.
25%
Built, at the Land Department site inspection of 20 August 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- October 2030
- Construction started
- December 2023
- Registered with the Land Department
- November 2023
- Developer
- Reportage Prime Properties
- Community
- Wadi Al Safa 7
- Units
- 1,753
- Escrow bank
- Al Masraf
- Name in Arabic
- ريبورتاج فيلدج 1
- Land Department project number
- 2784
- Land Department site inspections
- 5
Schedule
Between November 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around October 2030, more than three months after the December 2027 date registered with the Land Department.
Site inspections
20 August 2026
25%+4.3 pts
5 May 2026
21%+2.6 pts
10 February 2026
18%+7.0 pts
11 November 2025
11%+9.1 pts
11 April 2025
2.0%
Context
Wadi Al Safa 7 has 4 projects under construction, 20% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Reportage Village 1?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Reportage Village 1 be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Reportage Village 1 is built?
- 25%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 5 times since April 2025.
- Is Reportage Village 1 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Reportage Village 1?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Reportage Village 1?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- BiancaAlso by Reportage Prime Properties. 56%, Due December 2026.
- The AcresNearby in Wadi Al Safa 7. 25%.
- The Acres 3 & EstatesNearby in Wadi Al Safa 7. 15%, Due November 2027.
- The Acres 2 & Estates 2Nearby in Wadi Al Safa 7. 15%, Due May 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)