Verdana Residence construction progress
Verdana Residence in Dubai Investment Park First is 96% built at the Land Department inspection of June 2026. Developer Reportage Prime Properties. Completion registered for December 2025.
96%
Built, at the Land Department site inspection of 3 June 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- July 2026
- Construction started
- December 2022
- Registered with the Land Department
- March 2023
- Developer
- Reportage Prime Properties
- Community
- Dubai Investment Park First
- Units
- 224
- Escrow bank
- Al Masraf
- Name in Arabic
- فيردانا ريزيدنس
- Land Department project number
- 2470
- Land Department site inspections
- 9
Schedule
Verdana Residence was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 3.8 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
3 June 2026
96%+1.8 pts
6 February 2026
94%+26 pts
20 October 2025
68%+25 pts
17 March 2025
43%+24 pts
18 September 2024
19%+13 pts
26 March 2024
6.5%+4.5 pts
6 December 2023
2.0%+1.9 pts
26 July 2023
0.1%+0.1 pts
27 October 2022
0%
Context
Dubai Investment Park First has 9 projects under construction, 44% built on average. Verdana Residence is ahead of that average.
Reportage Prime Properties has 9 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Verdana Residence?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Verdana Residence be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Verdana Residence is built?
- 96%, measured at the Land Department site inspection on 3 June 2026. The Land Department engineers have inspected the site 9 times since October 2022.
- Is Verdana Residence delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Verdana Residence?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Verdana Residence?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana (Phase 1)Also by Reportage Prime Properties. 95%, Due December 2025, passed.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%.
- BiancaAlso by Reportage Prime Properties. 56%, Due December 2026.
- Verdana 2Also by Reportage Prime Properties. 56%.
- Olivia ResidencesNearby in Dubai Investment Park First. 38%, Due December 2026.
- Verdana 3Nearby in Dubai Investment Park First. 0.1%, Due September 2028.
- Verdana Residence 3Nearby in Dubai Investment Park First. 0%, Due September 2028.
- Verdana Residence 4Nearby in Dubai Investment Park First. 0%, Due September 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)