Reportage Village 1 construction photos
66 photos from 6 site inspections, newest first. The percentage is how much of Reportage Village 1 was built on the day of each visit.
11 November 202628% built
20 August 202625% built
5 May 202621% built
10 February 202618% built
11 November 202511% built
11 April 20252.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.