Verdana (Phase 1) construction progress
Verdana (Phase 1) in Dubai Investment Park First is 95% built at the Land Department inspection of June 2026. Developer Reportage Prime Properties. Completion registered for December 2025.
95%
Built, at the Land Department site inspection of 3 June 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- November 2026
- Construction started
- July 2022
- Registered with the Land Department
- May 2022
- Developer
- Reportage Prime Properties
- Community
- Dubai Investment Park First
- Units
- 178
- Escrow bank
- Al Masraf
- Name in Arabic
- فيردانا (المرحلة الاول)
- Land Department project number
- 2394
- Land Department site inspections
- 12
Schedule
Verdana (Phase 1) was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
3 June 2026
95%+1.9 pts
6 February 2026
93%+4.6 pts
6 November 2025
88%+19 pts
17 March 2025
69%+7.1 pts
23 December 2024
62%+22 pts
4 June 2024
40%+12 pts
26 March 2024
28%+5.2 pts
6 December 2023
23%+7.4 pts
25 September 2023
16%+3.9 pts
26 July 2023
12%+11 pts
Context
Dubai Investment Park First has 9 projects under construction, 44% built on average.
Reportage Prime Properties has 9 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Verdana (Phase 1)?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Verdana (Phase 1) be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Verdana (Phase 1) is built?
- 95%, measured at the Land Department site inspection on 3 June 2026. The Land Department engineers have inspected the site 12 times since November 2022.
- Is Verdana (Phase 1) delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Verdana (Phase 1)?
- The registered developer is Reportage Prime Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Verdana (Phase 1)?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Verdana(Phase 2)Also by Reportage Prime Properties. 94%.
- Verdana ResidenceAlso by Reportage Prime Properties. 96%, Due December 2025, passed.
- BiancaAlso by Reportage Prime Properties. 56%, Due December 2026.
- Verdana 2Also by Reportage Prime Properties. 56%.
- Olivia ResidencesNearby in Dubai Investment Park First. 38%, Due December 2026.
- Verdana 3Nearby in Dubai Investment Park First. 0.1%, Due September 2028.
- Verdana Residence 3Nearby in Dubai Investment Park First. 0%, Due September 2028.
- Verdana Residence 4Nearby in Dubai Investment Park First. 0%, Due September 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)