The Acres 2 & Estates 2 construction progress

The registered completion date for The Acres 2 & Estates 2 in Wadi Al Safa 7 is May 2028. At the last site inspection, in September 2026, it was 15% built. The developer is Dhre 2 Bts.

15%

Built, at the site inspection of 30 September 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
August 2031
Construction started
May 2025
First registered
March 2025
Developer
Dhre 2 Bts
Units
266
Escrow bank
Emirates NBD
Name in Arabic
ذا إيكرز 2 آند استيتس 2
Project number
3586
Site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 1.5 points a month. At that rate it would finish around August 2031, more than three months after its registered date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

15%+11 pts

  • The Acres 2 & Estates 2 construction site, inspection photo 1, 30 September 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 2, 30 September 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 3, 30 September 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 4, 30 September 2026

25 June 2026

3.7%+3.0 pts

  • The Acres 2 & Estates 2 construction site, inspection photo 1, 25 June 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 2, 25 June 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 3, 25 June 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 4, 25 June 2026

16 March 2026

0.7%

  • The Acres 2 & Estates 2 construction site, inspection photo 1, 16 March 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 2, 16 March 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 3, 16 March 2026
  • The Acres 2 & Estates 2 construction site, inspection photo 4, 16 March 2026

8 December 2025

0.7%+0.1 pts

  • The Acres 2 & Estates 2 construction site, inspection photo 1, 8 December 2025
  • The Acres 2 & Estates 2 construction site, inspection photo 2, 8 December 2025

29 August 2025

0.6%+0.6 pts

  • The Acres 2 & Estates 2 construction site, inspection photo 1, 29 August 2025
  • The Acres 2 & Estates 2 construction site, inspection photo 2, 29 August 2025

3 March 2025

0%

  • The Acres 2 & Estates 2 construction site, inspection photo 1, 3 March 2025
  • The Acres 2 & Estates 2 construction site, inspection photo 2, 3 March 2025

All 26 site photos, by inspection date

Context

Wadi Al Safa 7 has 4 projects under construction, 24% built on average.

Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Acres 2 & Estates 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Acres 2 & Estates 2 handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Acres 2 & Estates 2?
The Acres 2 & Estates 2 was 15% built at the site inspection on 30 September 2026. The site has been inspected 6 times since March 2025. The Land Department took 26 site photos at its inspections.
Is The Acres 2 & Estates 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building The Acres 2 & Estates 2?
The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for The Acres 2 & Estates 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.