Skip to content

The Acres 2 & Estates 2 construction progress

The Acres 2 & Estates 2 in Wadi Al Safa 7 is 15% built at the Land Department inspection of September 2026. Developer Dhre 2 Bts. Completion registered for May 2028.

15%

Built, at the Land Department site inspection of 30 September 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
August 2031
Construction started
May 2025
Registered with the Land Department
March 2025
Developer
Dhre 2 Bts
Units
266
Escrow bank
Emirates NBD
Name in Arabic
ذا إيكرز 2 آند استيتس 2
Land Department project number
3586
Land Department site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 1.5 points a month. At that rate it would finish around August 2031, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 September 2026

15%+11 pts

  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 1, 30 September 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 2, 30 September 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 3, 30 September 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 4, 30 September 2026

25 June 2026

3.7%+3.0 pts

  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 1, 25 June 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 2, 25 June 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 3, 25 June 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 4, 25 June 2026

16 March 2026

0.7%

  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 1, 16 March 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 2, 16 March 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 3, 16 March 2026
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 4, 16 March 2026

8 December 2025

0.7%+0.1 pts

  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 1, 8 December 2025
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 2, 8 December 2025

29 August 2025

0.6%+0.6 pts

  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 1, 29 August 2025
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 2, 29 August 2025

3 March 2025

0%

  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 1, 3 March 2025
  • The Acres 2 & Estates 2 construction site, Land Department inspection photo 2, 3 March 2025

All 26 site photos, by inspection date

Context

Wadi Al Safa 7 has 4 projects under construction, 20% built on average.

Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Acres 2 & Estates 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Acres 2 & Estates 2 be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around August 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Acres 2 & Estates 2 is built?
15%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 6 times since March 2025.
Is The Acres 2 & Estates 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building The Acres 2 & Estates 2?
The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for The Acres 2 & Estates 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.