Reportage Prime Properties projects under construction
Reportage Prime Properties has 9 projects under construction in Dubai, according to the Dubai Land Department. On average they are 51% built. 3 have passed their registered completion date. The next one due is Bianca, in December 2026.
- Verdana ResidenceDubai Investment Park First96%Due December 2025, passed
- Verdana (Phase 1)Dubai Investment Park First95%Due December 2025, passed
- Verdana(Phase 2)Dubai Investment Park First94%No date set
- BiancaWadi Al Safa 256%Due December 2026
- Verdana 2Dubai Investment Park First56%No date set
- Reportage Village 1Wadi Al Safa 725%Due December 2027
- Taormina Village 1Wadi Al Safa 320%No date set
- Verdana Residence 2Dubai Investment Park First20%Due April 2026, passed
- Reportage HillsAl Hebiah Fifth0.4%Due June 2028
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its full inspection history, recent site photos and whether it is keeping pace with that date.