Reportage Prime Properties projects under construction
Reportage Prime Properties has 9 projects under construction in Dubai. On average they are 52% built. 4 have passed their registered completion date. The next one due is Bianca, in December 2026.
- Verdana ResidenceDubai Investment Park First96%Due December 2025, passed
- Verdana (Phase 1)Dubai Investment Park First95%Due December 2025, passed
- Verdana(Phase 2)Dubai Investment Park First94%Due December 2025, passed
- BiancaWadi Al Safa 256%Due December 2026
- Verdana 2Dubai Investment Park First56%No date set
- Reportage Village 1Wadi Al Safa 728%Due December 2027
- Taormina Village 1Wadi Al Safa 320%Due December 2027
- Verdana Residence 2Dubai Investment Park First20%Due April 2026, passed
- Reportage HillsAl Hebiah Fifth0.4%Due June 2028
Questions
How many projects is Reportage Prime Properties building in Dubai?
9 projects are under construction, 52% built on average at the latest site inspections.
Which Reportage Prime Properties projects finish next?
By registered completion date: Bianca (December 2026, 56% built), Taormina Village 1 (December 2027, 20% built) and Reportage Village 1 (December 2027, 28% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Reportage Prime Properties projects delayed?
4 of its 9 projects have passed the registered completion date, among them Verdana Residence, Verdana (Phase 1) and Verdana(Phase 2). A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Reportage Prime Properties building?
Its projects are in Dubai Investment Park First (5), Al Hebiah Fifth (1) and Wadi Al Safa 2 (1), and 2 other communities.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.